Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue guide · CAISO

CAISO interconnection queue

How the cluster study process and intake scoring work, when the next application window opens, and what the public queue record shows at individual points of interconnection.

GridVision AI ResearchPublished Updated

CAISO at a glance

Process
A Cluster Study Process under CAISO's Resource Interconnection Standards. Projects under 5 MW can use a Fast Track path at any time of year.
Intake reforms
Interconnection Process Enhancements 2023 took effect on October 1, 2024. Projects are scored on commercial interest, project viability and system need, and CAISO can study projects up to 150% of available transmission capacity.
Cluster 15 intake
CAISO reported that scoring and filtering reduced Cluster 15 from 541 applications (347 GW) to 145 applications (approximately 68 GW), which received initial study results in November 2025.
Cluster 16 application window
The tariff sets an annual window from October 1 to October 15 beginning in 2026. CAISO's portal opened for preparing applications on September 4, 2026, with submissions blocked until October 1, 2026.
Latest rule change
FERC accepted Interconnection Process Enhancements 5.0 in part on August 4, 2026, effective August 5, 2026.
Queue size
CAISO's July 2025 board briefing put active projects from Cluster 14 and earlier at about 185 GW.

Sources: CAISO, Interconnection request and study; CAISO news release, “FERC approves ISO interconnection reforms,” October 1, 2024; CAISO Energy Matters, “2025 Year in Review,” December 4, 2025; CAISO tariff Appendix KK, Resource Interconnection Standards (as of June 25, 2025); CAISO notice, GRIP portal available for Cluster 16 applications, September 4, 2026; FERC order on CAISO Interconnection Process Enhancements 5.0, August 4, 2026; CAISO board briefing on interconnection process enhancements and the queue, July 2025.

Facts checked September 16, 2026.

How the CAISO process works

CAISO's tariff (Appendix KK) sets out the cluster sequence and its target durations:

  1. 01Cluster application windowA 15-day window, October 1–15 each year from 2026.
  2. 02Customer engagement windowA 90-calendar-day period.
  3. 03Cluster studyTargeted for completion 150 calendar days after the customer engagement window closes. A reassessment is performed before each cluster study.
  4. 04Interconnection facilities study120 days planned.
  5. 05Transmission plan deliverability allocation
  6. 06Generator interconnection agreement

Intake scoring and zonal study limits from Interconnection Process Enhancements apply to Cluster 15 and later clusters. The current tariff governs any live project.

Sources: CAISO tariff Appendix KK, Resource Interconnection Standards (as of June 25, 2025); CAISO news release, “FERC approves ISO interconnection reforms,” October 1, 2024.

What the public record shows at CAISO points of interconnection

Across the 37 CAISO points of interconnection GridVision has published so far, the Berkeley Lab dataset records 473 interconnection requests filed between 1999 and 2023.

Outcomes of interconnection requests at the published CAISO points of interconnection
OutcomeRequestsCapacity (MW)
Reached commercial operation375,975
Withdrew30790,346
Still active12936,105
Total473132,425

For the requests that were built, the median time from request to commercial operation was 6.8 years. For those that withdrew, the median time from request to withdrawal was 1.6 years.

These 37 nodes are not a random sample of CAISO, and a pattern at one point of interconnection does not transfer to another. The dataset records what happened, not why.

Published CAISO point-of-interconnection retrospectives
Point of interconnectionStateRequestsBuiltWithdrawnActive
Hoodoo Wash Switchyard 500 kVArizona13256
Delaney Substation 500 kVArizona / California10073
Antelope 230 kVCalifornia9054
Antelope Substation 66 kVCalifornia14590
Arco 230 kVCalifornia14095
Arco Substation 70 kVCalifornia120111
Birds Landing 230 kVCalifornia182115
Borrego Substation 69 kVCalifornia111100
Boulevard East Substation 138 kVCalifornia9072
Colorado River Substation 230 kVCalifornia163112
Devers Substation 230 kVCalifornia8161
Gates Substation 230 kVCalifornia7160
Highwind Substation 230 kVCalifornia141130
Kramer Substation 230 kVCalifornia9135
Lamont Substation 115 kVCalifornia11083
Los Banos 230 kVCalifornia11083
Los Banos 500 kVCalifornia130112
Lugo 500 kVCalifornia180711
Manning 500 kVCalifornia240159
Mendota Substation 115 kVCalifornia171124
Mira Loma Substation 230 kVCalifornia12084
Otay Mesa Switchyard 230 kVCalifornia14653
Pisgah Substation 230 kVCalifornia170143
Quinto Switching Station 230 kVCalifornia12084
Red Bluff Substation 500 kVCalifornia10064
Schindler Substation 115 kV BusCalifornia9090
Stroud switching station 70 kVCalifornia6150
Tranquility 230 kVCalifornia14068
Victor Substation 230 kVCalifornia6150
Vincent Substation 230 kVCalifornia16295
Whirlwind Substation 230 kVCalifornia236107
Windhub Substation 230 kVCalifornia16385
Control Substation 115 kV busNevada140140
Mohave Substation 500 kVNevada / California13094
Sloan Canyon 230 kVNevada / California9081
Trout Canyon Substation 230 kVNevada / California14059
Valley Switch 230 kVNevada / California10046

States with CAISO requests

Requests at points of interconnection in these states are studied in the CAISO queue. The count is how many of that state's requests the dataset places in this market; a state with requests in more than one market appears under each.

Questions to answer before advancing a CAISO queue position

  • Is the project headed for a Deliverable Zone or a Merchant Zone, and what evidence supports the intake score you expect?
  • Does the project need a transmission plan deliverability allocation, and what is the plan if it does not receive one?
  • Which reassessment results could change your cost responsibility before the next financial commitment?
  • Which unknowns could change the answer, who owns each one, and when will it be resolved?

Weighing whether to advance a CAISO queue position?

Bring the decision, and get back a management-ready decision record: what is verified, what is assumed, what is still unknown, and what to do next.

Request a qualification conversation

Sources

Facts checked September 16, 2026. Process rules and queue data change; the governing tariff, manuals and study documents control any live project.