CAISO · Nevada / California · Public-record retrospective
Mohave Substation 500 kV: interconnection queue history
Nine of thirteen requests withdrew; four are still in the queue.
GridVision AI ResearchUpdated
Thirteen interconnection requests since 2006: 9 withdrew and 4 remain active.
- Built
- 0
- Withdrawn
- 9
- Still in queue
- 4
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2006-05-26 | MOJAVE SOLAR PARK 1 | Solar | 635 MW | Withdrawn2008-10-13 |
| 2016-05-02 | SOUTHLAND | Solar | 380.1 MW | Withdrawn2021-06-11 |
| 2016-05-02 | ARIZONA MOHAVE SOLAR | Solar | 520.6 MW | Withdrawn2017-03-09 |
| 2018-04-16 | ARIDA SOLAR FARM | Solar + battery | 370 MW | Still in queue |
| 2019-04-15 | BULLHEAD SOLAR | Solar + battery | 400 MW | Withdrawn2020-03-04 |
| 2019-04-15 | ARIDA 2 SOLAR FARM | Solar + battery | 700 MW | Still in queue |
| 2020-04-15 | ARIDA 3 SOLAR FARM | Solar + battery | 450 MW | Still in queue |
| 2021-04-15 | STERLING | Solar + battery | 250 MW | Still in queue |
| 2023-04-17 | Silver Storage | Battery | 358 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Hiko | Battery | 359.798 MW | Withdrawn2025-04-29 |
| 2023-04-17 | Thar Energy Storage | Battery | 513 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Icarus Wind and Solar | Solar + battery | 717.8 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Icarus Solar | Solar + battery | 718.2 MW | Withdrawn2025-12-02 |
What the record shows
- 4,602 MW of the 6,372 MW filed here withdrew.
- The largest request filed here, 718 MW (solar + battery), withdrew 2.6 years after filing.
- Five requests were filed on 2023-04-17; all of them withdrew.
- Two of the 9 withdrawals came within a year of filing.
- By technology, the requests here were solar + battery 7, battery 3, solar 3.
- The longest-standing active request here was filed on 2018-04-16.
- The dataset records this point of interconnection under six spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Four requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · Nevada / CaliforniaTrout Canyon Substation 230 kV14 requests · 0 built · 5 withdrawn · 9 still in queueRead the record
- CAISO · Nevada / CaliforniaValley Switch 230 kV10 requests · 0 built · 4 withdrawn · 6 still in queueRead the record
- CAISO · Nevada / CaliforniaSloan Canyon 230 kV9 requests · 0 built · 8 withdrawn · 1 still in queueRead the record
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.