CAISO · Nevada / California · Public-record retrospective
Sloan Canyon 230 kV: interconnection queue history
Eight of nine requests withdrew; one is still in the queue.
GridVision AI ResearchUpdated
Nine interconnection requests since 2016: 8 withdrew and 1 remains active.
- Built
- 0
- Withdrawn
- 8
- Still in queue
- 1
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2016-05-02 | ROCCASECCA BESS | Battery | 303 MW | Still in queue |
| 2019-04-15 | BLACK HILLS PLAYA A SOLAR | Solar + battery | 102.3 MW | Withdrawn2019-07-24 |
| 2019-04-15 | BLACK HILLS PLAYA B SOLAR | Solar + battery | 102.3 MW | Withdrawn2019-07-24 |
| 2019-04-15 | SLOAN ENERGY CENTER | Solar + battery | 459.54 MW | Withdrawn2020-03-12 |
| 2023-04-17 | Dutchmans Pass | Solar + battery | 300 MW | Withdrawn2024-12-02 |
| 2023-04-17 | North Highland | Solar + battery | 400 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Sandy Valley | Solar + battery | 400 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Stonehaven | Solar + battery | 427 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Reed Meadow | Battery | 565.769988 MW | Withdrawn2025-04-28 |
What the record shows
- 2,757 MW of the 3,060 MW filed here withdrew.
- The largest request filed here, 566 MW (battery), withdrew 2.0 years after filing.
- Five requests were filed on 2023-04-17; all of them withdrew.
- Three of the 8 withdrawals came within a year of filing.
- By technology, the requests here were solar + battery 7, battery 2.
- The longest-standing active request here was filed on 2016-05-02.
- The dataset records this point of interconnection under four spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- One request is unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · Nevada / CaliforniaTrout Canyon Substation 230 kV14 requests · 0 built · 5 withdrawn · 9 still in queueRead the record
- CAISO · Nevada / CaliforniaMohave Substation 500 kV13 requests · 0 built · 9 withdrawn · 4 still in queueRead the record
- CAISO · Nevada / CaliforniaValley Switch 230 kV10 requests · 0 built · 4 withdrawn · 6 still in queueRead the record
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.