CAISO · Nevada / California · Public-record retrospective
Trout Canyon Substation 230 kV: interconnection queue history
Five of fourteen requests withdrew; nine are still in the queue.
GridVision AI ResearchUpdated
Fourteen interconnection requests since 2019: 5 withdrew and 9 remain active.
- Built
- 0
- Withdrawn
- 5
- Still in queue
- 9
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2019-04-12 | BONANZA PEAK SOLAR FARM | Solar + battery | 441 MW | Still in queue |
| 2019-04-15 | ROUGH HAT HYBRID SOLAR | Solar + battery | 204 MW | Still in queue |
| 2019-04-15 | YELLOW PINE 3 | Solar + battery | 261.954 MW | Still in queue |
| 2020-04-15 | ROUGH HAT 2 | Solar + battery | 203.8 MW | Still in queue |
| 2020-04-15 | CALVADA SPRINGS SOLAR | Solar + battery | 250 MW | Still in queue |
| 2020-04-15 | PURPLE SAGE ENERGY CENTER | Solar + battery | 409.2 MW | Still in queue |
| 2021-04-15 | LARREA SOLAR | Solar + battery | 307 MW | Still in queue |
| 2021-04-15 | SUNBAKED SOLAR | Solar + battery | 508.56 MW | Still in queue |
| 2021-04-15 | MOSEY | Solar + battery | 543.856 MW | Still in queue |
| 2023-04-17 | Rock Canyon | Solar + battery | 250 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Dumont | Solar + battery | 427 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Crossover | Solar + battery | 527 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Campito Peak | Battery | 565.769988 MW | Withdrawn2025-04-28 |
| 2023-04-17 | Borderline Solar | Solar + battery | 638.1349 MW | Withdrawn2025-05-01 |
What the record shows
- 2,408 MW of the 5,537 MW filed here withdrew.
- The largest request filed here, 638 MW (solar + battery), withdrew 2.0 years after filing.
- Five requests were filed on 2023-04-17; all of them withdrew.
- None of the 5 withdrawals came within a year of filing; the quickest took 1.6 years.
- By technology, the requests here were solar + battery 13, battery 1.
- The longest-standing active request here was filed on 2019-04-12.
- The dataset records this point of interconnection under three spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Nine requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · Nevada / CaliforniaMohave Substation 500 kV13 requests · 0 built · 9 withdrawn · 4 still in queueRead the record
- CAISO · Nevada / CaliforniaValley Switch 230 kV10 requests · 0 built · 4 withdrawn · 6 still in queueRead the record
- CAISO · Nevada / CaliforniaSloan Canyon 230 kV9 requests · 0 built · 8 withdrawn · 1 still in queueRead the record
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.