Choosing a point of interconnection is a capital-allocation decision. This guide sets out what to compare between candidate POIs, what the public queue record can and cannot tell you, and which unknowns to resolve before a POI earns its next dollar of study spend.

GridVision AI ResearchPublished Updated

What is a point of interconnection?

A point of interconnection (POI) is where a generating facility, storage project or large load connects to the grid: usually a named substation bus, a new switching station or a tap on an existing line, at a stated voltage. The POI in an interconnection request determines which facilities are studied, which network upgrades the project can be assigned, and which other requests it is studied alongside.

Why POI choice carries more weight under cluster studies

FERC Order No. 2023 replaced serial, first-come, first-served queues with cluster studies and a first-ready, first-served standard. Interconnection customers now demonstrate site control, post deposits that rise as a project advances, and face withdrawal penalties when leaving affects other projects (FERC).

That puts more capital at stake before study results arrive. PJM's first cycle under its reformed process closed on April 27, 2026 with 811 projects and 220 GW of nameplate capacity (PJM). Cycle 1 applications required a readiness deposit of $4,000 per MW, alongside a study deposit of $75,000 to $400,000 depending on project size (PJM). See the PJM interconnection queue page for how that process runs.

The long-run record shows why the choice deserves discipline: 13% of the capacity that requested interconnection from 2000 to 2020 had reached commercial operation by the end of 2025, and 75% had withdrawn (Berkeley Lab).

Six comparisons to make between candidate POIs

Record the same fields for every candidate so the comparison is fair.

  1. 01

    Electrical position

    Voltage, bus configuration and nearby constraints, plus the network model you are relying on. If you screen with DC power flow or distribution factors (PTDF/LODF), record the model source, version and date. A screen is only as current as its model.

  2. 02

    Queue context at the node

    Requests active at or electrically near the POI (size, technology, cluster), and how earlier requests at the same POI resolved.

  3. 03

    Upgrade exposure

    Network upgrades identified in study reports for this POI and its neighbors, and whether each is in service, under construction or still conceptual.

  4. 04

    Schedule dependencies

    Transmission projects, affected-system studies and prior-cycle results that your schedule depends on.

  5. 05

    Site fit

    Site control, gen-tie route and permitting constraints between the site and the POI.

  6. 06

    Commercial fit

    The interconnection service you need (energy-only or capacity), market access, and the offtake assumptions the project relies on.

Keep verified facts, project inputs, assumptions and unknowns in separate columns. A missing value is a diligence task, not a number to estimate.

What the public queue record shows at individual POIs

Node-level history rarely looks like the national average. GridVision's public-record retrospectives read the Berkeley Lab project-level dataset one point of interconnection at a time:

  • Same-day filings, different outcomes. At Colorado River Substation 230 kV in CAISO, three requests were filed on April 30, 2015. Two reached commercial operation, after 7.5 and 8.5 years; the largest of the three, at 600 MW, withdrew in 2017.
  • Filed capacity is not built capacity. At Gates Substation 230 kV in CAISO, seven requests totaled 1,144 MW. One 20 MW battery reached operation, 9.4 years after its request.
  • Some nodes resolve very differently. At Sweetwater 230 kV in SPP, four of five requests were built.
  • Request structure varies. At Hatfield 500 kV in PJM, the gas project that was built had been filed as three separate requests.

The dataset records outcomes and dates, not reasons. It does not say why any project withdrew, and a pattern at one POI does not transfer to another. Use node history to sharpen diligence questions, not as a forecast.

A decision rule for advancing a POI

Advance a candidate POI to the next commitment only when:

  • every comparison field is filled, or each gap has an owner and a due date;
  • every material fact has a source and a retrieval date;
  • the POI is still preferred after you write down the unknowns that could change cost, schedule or deliverability.

Pause or deprioritize a POI when an unknown that could change the decision cannot be resolved before the next financial commitment: a readiness deposit, a study agreement or a decision point.

POI comparison checklist

Fields to record for each candidate point of interconnection
FieldWhat to recordTypical evidence
POISubstation or line, voltage, transmission ownerQueue data, transmission owner documents
Queue contextActive and historical requests at the POI, with outcomesPublic queue data
Model basisNetwork model source, version and dateAuthorized network model
Screening resultsDC power flow, PTDF and LODF results and their limitsScreening output, when an authorized model is available
Upgrade exposureIdentified upgrades and their statusStudy reports
Schedule dependenciesPrior-cycle results, affected systems, transmission projectsISO/RTO and transmission owner documents
Site fitSite control, gen-tie route, permittingProject records
Commercial fitService type, market access, offtake assumptionsProject inputs and stated assumptions
UnknownsWhat could change the decision, its owner and due dateDiligence plan

For the full evidence model, see the Interconnection Due Diligence Checklist and the Interconnection Due Diligence Report 2026.

Frequently asked questions

What is a point of interconnection (POI)?
The substation bus, switching station or line location where a project connects to the grid, stated at a voltage in the interconnection request.
Is a POI the same as a substation?
Often, but not always. A POI can also be a new switching station or a tap on an existing transmission line.
Can I change my POI after submitting an interconnection request?
Most tariffs restrict POI changes once a request is submitted, and many treat them as material modifications. Check the governing tariff and manual (for PJM, Manual 14H) before relying on a change.
Does a lot of queued capacity at a POI mean the POI is constrained?
Not by itself. Queued capacity shows interest, not what will be built or what the network can accept. Study results and the network model are the evidence for that.
How does GridVision AI help with POI decisions?
GridVision AI turns the evidence for candidate POIs into an executive-ready decision record: what is verified, what is assumed, what is still unknown, and whether each position should advance, be reviewed or be deprioritized.

Comparing POIs for a live project?

Bring one decision, and get back a decision record your management team can act on.

Bring One Live Decision

Sources

Sources checked September 16, 2026. Process rules and queue data change; verify the current tariff, provider portal and study documents before relying on a project conclusion.