Interconnection queue guide · PJM
PJM interconnection queue
How the reformed cycle process works, what the first cycle received, and what the public queue record shows at individual points of interconnection.
GridVision AI ResearchPublished Updated
PJM at a glance
- Process
- A cycle-based, first-ready, first-served process that replaced first-come, first-served.
- Cycle 1 application deadline
- April 27, 2026.
- Cycle 1 requests
- 811 projects and 220 GW of nameplate capacity.
- Largest resource types in Cycle 1
- Natural gas 105.8 GW (157 projects); storage 66.5 GW (349); nuclear 17.9 GW (27); solar 14.8 GW (142).
- Expected study duration
- One to two years, depending on the impact of an individual project.
- Transition backlog
- In September 2025, PJM said the remaining transition backlog of about 46 GW would be processed by the end of 2026.
Sources: PJM Inside Lines, “Over 800 New Generation Projects Seek To Connect Under PJM’s Reformed Process,” April 29, 2026; PJM Inside Lines, “PJM Completes Interconnection Reform Transition Cycle 1 Studies,” September 22, 2025.
Facts checked September 16, 2026.
How the PJM process works
PJM studies new service requests in cycles. Each cycle moves through the same sequence:
- 01ApplicationSubmit the application, study deposit, readiness deposit and site-control evidence by the cycle deadline.
- 02Application reviewPJM checks each application for completeness.
- 03Phase 1, then Decision Point 1
- 04Phase 2, then Decision Point 2
- 05Phase 3, then Decision Point 3
- 06Final agreement
At each decision point, the project owner decides whether to continue into the next phase. Deposit and withdrawal terms are set by PJM's tariff and Manual 14H, which govern any live project.
Sources: PJM, “Cycle 01 Application Requirements and NextGen Process,” Interconnection Process Subcommittee, January 2026; PJM Manual 14H: New Service Requests Cycle Process.
What a PJM Cycle 1 application required
PJM's January 2026 presentation to its Interconnection Process Subcommittee listed these Cycle 1 application requirements:
- Study deposit
- One deposit for the whole cycle, from $75,000 (0–20 MW) to $400,000 (over 750 MW). 10% is non-refundable, and the developer pays the full study cost.
- Readiness deposit
- $4,000 per MW of the larger of the energy and capacity values, by letter of credit or wire transfer.
- Site control
- 100% of the generating facility, including the high side of the main power transformer, valid for one year from the application deadline. Minimum acreage: solar 5 acres/MW, wind 30 acres/MW, battery 1 acre per 100 MWh.
- Agreements and data
- An executed Application and Studies Agreement, with technical data entered in PJM's NextGen platform.
What the public record shows at PJM points of interconnection
Across the 35 PJM points of interconnection GridVision has published so far, the Berkeley Lab dataset records 254 interconnection requests filed between 1997 and 2025.
| Outcome | Requests | Capacity (MW) |
|---|---|---|
| Reached commercial operation | 83 | 6,191 |
| Withdrew | 131 | 37,288 |
| Still active | 40 | 5,439 |
| Total | 254 | 48,918 |
For the requests that were built, the median time from request to commercial operation was 3.3 years. For those that withdrew, the median time from request to withdrawal was 2.3 years.
These 35 nodes are not a random sample of PJM, and a pattern at one point of interconnection does not transfer to another. The dataset records what happened, not why.
States with PJM requests
Requests at points of interconnection in these states are studied in the PJM queue. The count is how many of that state's requests the dataset places in this market; a state with requests in more than one market appears under each.
- Pennsylvania 1,814
- Virginia 1,326
- New Jersey 1,183
- Ohio 866
- Illinois 609
- Maryland 556
- Indiana 356
- West Virginia 237
- Kentucky 213
- North Carolina 191
- Delaware 149
- Michigan 47
- Tennessee 5
- South Dakota 3
- Iowa 2
- North Dakota 1
Questions to answer before advancing a PJM queue position
- Which study results does your cost allocation rest on, and which of them depend on requests that could still withdraw?
- Which network upgrades are shared with other requests, and what happens to your share if those requests leave?
- Under the current tariff, what is at risk if you continue, and what is forfeited if you withdraw now?
- Which unknowns could change the answer, who owns each one, and when will it be resolved?
Related reading
Weighing whether to advance a PJM queue position?
Bring the decision, and get back a management-ready decision record: what is verified, what is assumed, what is still unknown, and what to do next.
Request a qualification conversationSources
- PJM Inside Lines, “Over 800 New Generation Projects Seek To Connect Under PJM’s Reformed Process,” April 29, 2026
- PJM Inside Lines, “PJM Completes Interconnection Reform Transition Cycle 1 Studies,” September 22, 2025
- PJM, “Cycle 01 Application Requirements and NextGen Process,” Interconnection Process Subcommittee, January 2026
- PJM Manual 14H: New Service Requests Cycle Process
- Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0)
Facts checked September 16, 2026. Process rules and queue data change; the governing tariff, manuals and study documents control any live project.