Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

West Virginia interconnection queue

237 interconnection requests have been filed at points of interconnection in West Virginia since 2000, totalling 30 GW. Of that capacity, 8.7% reached commercial operation and 68.4% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

30 GW
of capacity requested in West Virginia since 2000
8.7%
of it reached commercial operation; 68.4% withdrew
11 GW
filed in the last six years (96 requests), of which 41.2% is still in the queue

Which markets West Virginia requests sit in

A state is a location, not a market. Requests at West Virginia points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
PJM23730 GW8.7%68.4%

Process pages: PJM.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar605 GW1.9%72.7%
Other464 GW27.1%69.2%
Wind424 GW20.8%59.8%
Gas4213 GW3.0%65.6%
Hybrid253 GW7.3%70.7%
Battery222 GW1.9%96.1%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2000100 MW
  • 20013 GW
  • 2002572 MW
  • 2003121 MW
  • 2004632 MW
  • 20052 GW
  • 2006678 MW
  • 2007251 MW
  • 20081 GW
  • 2009469 MW
  • 2010152 MW
  • 2011277 MW
  • 201281 MW
  • 20131 GW
  • 2014170 MW
  • 20152 GW
  • 2016631 MW
  • 2017410 MW
  • 20182 GW
  • 20192 GW
  • 20201 GW
  • 20214 GW
  • 20222 GW
  • 2023321 MW
  • 20254 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Hopkins 138 kV6 requests in the dataset
  • George Washington 138kV4 requests in the dataset
  • Glen Falls 138kV3 requests in the dataset
  • Tidd-Wylie Ridge 345kV3 requests in the dataset
  • Grassy Falls 138kV3 requests in the dataset
  • North Franklin 138kV3 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.