Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Virginia interconnection queue

1,334 interconnection requests have been filed at points of interconnection in Virginia since 2000, totalling 129 GW. Of that capacity, 11.0% reached commercial operation and 65.6% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

129 GW
of capacity requested in Virginia since 2000
11.0%
of it reached commercial operation; 65.6% withdrew
56 GW
filed in the last six years (710 requests), of which 34.5% is still in the queue

Which markets Virginia requests sit in

A state is a location, not a market. Requests at Virginia points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
PJM1,326129 GW11.1%65.4%
Southeast8524 MW0.0%100.0%

Process pages: PJM.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar71848 GW8.7%63.0%
Battery27823 GW0.1%57.2%
Hybrid1099 GW0.2%86.6%
Gas10233 GW23.8%67.9%
Other825 GW46.2%53.4%
Wind4511 GW0.1%74.9%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2000960 MW
  • 2001522 MW
  • 2002293 MW
  • 20037 MW
  • 200489 MW
  • 20052 GW
  • 20063 GW
  • 20072 GW
  • 20084 GW
  • 20092 GW
  • 20102 GW
  • 20114 GW
  • 20123 GW
  • 20133 GW
  • 2014685 MW
  • 2015887 MW
  • 201610 GW
  • 20175 GW
  • 201814 GW
  • 201915 GW
  • 202014 GW
  • 202118 GW
  • 20229 GW
  • 20233 GW
  • 202513 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Hopewell-Surry 230 kV9 requests in the dataset
  • Harmony Village-Shackleford 115 kV8 requests in the dataset
  • Hopewell 230kV6 requests in the dataset
  • Kings Dominion DP 115 kV6 requests in the dataset
  • Hickory 34.5 kV6 requests in the dataset
  • St. Johns 115 kV6 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Published retrospectives in Virginia

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.