PJM · Virginia · Public-record retrospective
Chesterfield 230 kV: interconnection queue history
3,190 MW filed. 66 MW built.
GridVision AI ResearchUpdated
Nine interconnection requests since 2007: 3 reached commercial operation, 3 withdrew, and 3 remain active.
- Built
- 3
- Withdrawn
- 3
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2007-01-11 | Chesterfield Unit #5 | Coal | 19 MW | Built2011-06-01 · 4.4 yrs |
| 2007-07-31 | Chesterfield Unit #5 | Coal | 20 MW | Built2011-06-01 · 3.8 yrs |
| 2007-07-31 | Chesterfield Unit #6 | Coal | 27 MW | Built2010-12-01 · 3.3 yrs |
| 2011-07-28 | (unnamed) | Gas | 1575 MW | Withdrawn2012-12-05 |
| 2019-09-18 | Chesterfield CT Units 1 and 2 | Gas | 569 MW | Still in queue |
| 2019-09-18 | Chesterfield CT Units 3&4 | Gas | 569 MW | Still in queue |
| 2021-03-19 | (unnamed) | Battery | 150 MW | Withdrawn2024-12-17 |
| 2025-02-03 | (unnamed) | Battery | 200 MW | Withdrawn2025-11-25 |
| 2025-02-04 | (unnamed) | Battery | 60.82 MW | Still in queue |
What the record shows
- 1,925 MW of the 3,190 MW filed here withdrew, and 66 MW reached commercial operation.
- Completions here took between 3.3 and 4.4 years from request to commercial operation (median 3.8).
- The largest request filed here, 1,575 MW (gas), withdrew 1.4 years after filing.
- Two requests were filed on 2019-09-18; all of them remain active.
- One of the 3 withdrawals came within a year of filing.
- By technology, the requests here were battery 3, coal 3, gas 3.
- The longest-standing active request here was filed on 2019-09-18.
- The dataset records this point of interconnection under two spellings, which are combined here.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- Three requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- PJM · VirginiaAxton 138 kV5 requests · 1 built · 4 withdrawn · 0 still in queueRead the record
- PJM · VirginiaHopewell 230 kV6 requests · 3 built · 3 withdrawn · 0 still in queueRead the record
- PJM · VirginiaFour Rivers 230 kV5 requests · 3 built · 2 withdrawn · 0 still in queueRead the record
- PJM · VirginiaHopewell-Surry 230 kV5 requests · 3 built · 2 withdrawn · 0 still in queueRead the record
How the PJM process works today: PJM interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.