PJM · Virginia · Public-record retrospective

Harmony Village-Shackleford 115 kV: interconnection queue history

Three of ten requests reached commercial operation.

GridVision AI ResearchUpdated

Ten interconnection requests since 2016: 3 reached commercial operation and 7 remain active.

Built
3
Withdrawn
0
Still in queue
7

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2016-09-22Walnut Solar ISolar50 MWStill in queue
2017-03-14Walnut Solar ISolar20 MWStill in queue
2017-08-03Carvers Creek SolarSolar50 MWBuilt2024-08-22 · 7.1 yrs
2018-01-20Walnut Solar ISolar20 MWStill in queue
2018-04-07Walnut Solar ISolar20 MWStill in queue
2018-09-28Carvers Creek SolarSolar20 MWBuilt2025-12-04 · 7.2 yrs
2018-09-28Carvers Creek SolarSolar80 MWBuilt2025-12-04 · 7.2 yrs
2018-10-05Walnut Solar ISolar20 MWStill in queue
2019-04-04Walnut Solar ISolar19.9 MWStill in queue
2023-02-27(unnamed)Solar40.7 MWStill in queue

What the record shows

  • 150 MW of the 341 MW filed here reached commercial operation.
  • Completions here took between 7.1 and 7.2 years from request to commercial operation (median 7.2).
  • The largest request filed here, 80 MW (solar), reached operation 7.2 years after filing.
  • Two requests were filed on 2018-09-28; all of them reached operation.
  • The longest-standing active request here was filed on 2016-09-22.
  • The dataset records this point of interconnection under two spellings, which are combined here.

What a decision record would have to make explicit

  • None of the resolved requests at this node reached operation, and the public record does not say why.
  • Seven requests are unresolved, so the outcome counts at this node can still change.
  • The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.