PJM · Virginia · Public-record retrospective
Harmony Village-Shackleford 115 kV: interconnection queue history
Three of ten requests reached commercial operation.
GridVision AI ResearchUpdated
Ten interconnection requests since 2016: 3 reached commercial operation and 7 remain active.
- Built
- 3
- Withdrawn
- 0
- Still in queue
- 7
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2016-09-22 | Walnut Solar I | Solar | 50 MW | Still in queue |
| 2017-03-14 | Walnut Solar I | Solar | 20 MW | Still in queue |
| 2017-08-03 | Carvers Creek Solar | Solar | 50 MW | Built2024-08-22 · 7.1 yrs |
| 2018-01-20 | Walnut Solar I | Solar | 20 MW | Still in queue |
| 2018-04-07 | Walnut Solar I | Solar | 20 MW | Still in queue |
| 2018-09-28 | Carvers Creek Solar | Solar | 20 MW | Built2025-12-04 · 7.2 yrs |
| 2018-09-28 | Carvers Creek Solar | Solar | 80 MW | Built2025-12-04 · 7.2 yrs |
| 2018-10-05 | Walnut Solar I | Solar | 20 MW | Still in queue |
| 2019-04-04 | Walnut Solar I | Solar | 19.9 MW | Still in queue |
| 2023-02-27 | (unnamed) | Solar | 40.7 MW | Still in queue |
What the record shows
- 150 MW of the 341 MW filed here reached commercial operation.
- Completions here took between 7.1 and 7.2 years from request to commercial operation (median 7.2).
- The largest request filed here, 80 MW (solar), reached operation 7.2 years after filing.
- Two requests were filed on 2018-09-28; all of them reached operation.
- The longest-standing active request here was filed on 2016-09-22.
- The dataset records this point of interconnection under two spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Seven requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- PJM · VirginiaAxton 138 kV5 requests · 1 built · 4 withdrawn · 0 still in queueRead the record
- PJM · VirginiaHopewell 230 kV6 requests · 3 built · 3 withdrawn · 0 still in queueRead the record
- PJM · VirginiaFour Rivers 230 kV5 requests · 3 built · 2 withdrawn · 0 still in queueRead the record
- PJM · VirginiaHopewell-Surry 230 kV5 requests · 3 built · 2 withdrawn · 0 still in queueRead the record
How the PJM process works today: PJM interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.