PJM · Ohio

AES Tait Energy Storage filed twice, and both were built.

Tait 69 kV

Five interconnection requests since 2006: 4 reached commercial operation, 1 withdrew.

Built
4
Withdrawn
1
Still in queue
0

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2006-09-29Tait Generating Units 4-7Gas15 MWBuilt2007-05-01 · 0.6 yrs
2007-07-05Tait Generating StationGas13 MWBuilt2007-10-05 · 0.3 yrs
2012-11-02AES Tait Energy StorageBattery12 MWBuilt2013-08-27 · 0.8 yrs
2013-04-19AES Tait Energy StorageBattery8 MWBuilt2013-09-24 · 0.4 yrs
2014-10-30(unnamed)Battery20 MWWithdrawn2017-12-13

What the record shows

  • One of the five requests at this node withdrew, and 20 MW of the 68 MW filed here never reached operation.
  • Completions here took between 0.3 and 0.8 years from request to commercial operation.
  • The largest request ever filed here, 20 MW, withdrew 3.1 years after filing.
  • AES Tait Energy Storage appears two times in the queue at this node, filed between 2012 and 2013, of which two reached operation.
  • No request at this node remains active, so its record is settled.

What a decision record would have to make explicit

  • With five requests, nothing at this node generalises to another; it is a record, not a rate.
  • The dataset records no withdrawal reasons, study costs or upgrade assignments, so those remain unknowns on this record.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.