Interconnection guide
Stay in the interconnection queue or withdraw?
Cluster studies turn a queue position into a series of paid commitments. At each decision point the question is the same: does the evidence justify the next deposit? This guide sets out what changes at those points and what to check before you answer.
GridVision AI ResearchPublished Updated
Why the decision points matter more now
Most queued capacity never reaches operation. Of the capacity that requested interconnection from 2000 to 2020, 13% had reached commercial operation by the end of 2025 and 75% had withdrawn (Berkeley Lab; see the queue statistics).
FERC Order No. 2023 made staying in the queue progressively more expensive. Interconnection customers post a commercial readiness deposit at the beginning of each study, and that deposit shifts from one based on facility size to increasing percentages of the customer's identified network upgrade costs. Transmission providers must impose a withdrawal penalty when a withdrawal has a material impact on the cost or timing of requests with an equal or lower queue position (FERC).
Order No. 2023-A added two limits: withdrawal penalties cannot exceed the amount collected from the customer, and no penalty applies if the withdrawal has no material impact on any request in the same cluster. It also allowed surety bonds as deposits (FERC).
What changes at each decision point
Each transmission provider sets its own amounts and timing in its tariff. Three examples:
- PJM. Each decision point is 30 calendar days. Readiness Deposit No. 1 is $4,000 per MW, and a request withdrawn before Phase I starts does not forfeit it (Manual 14H). See the PJM interconnection queue page.
- SPP. Financial security steps up at each decision point: $4,000 per MW to enter Phase One; at Decision Point 1, the greater of 10% of a cost factor (less the first security) or $4,000 per MW; at Decision Point 2, 20% of total upgrade costs less the securities already posted (SPP). See the SPP interconnection queue page.
- ISO New England (as proposed in January 2024). For large generators, a first readiness deposit of twice the $250,000 study deposit, then 5% of network upgrade costs at the cluster restudy, 10% at the facilities study, and 20% of network upgrades and interconnection facilities when the agreement is signed, with penalty-free withdrawal if network upgrade costs rise by more than 25% in the cluster restudy report or more than 100% in the facilities study report. ISO New England noted the proposal could change (ISO-NE). See the ISO-NE interconnection queue page.
The pattern is the same everywhere: the later you withdraw, the more is at stake, and the rules for recovering it depend on how much your costs changed and whether leaving affects anyone else.
Treat cost changes as the first signal
In Berkeley Lab's PJM analysis, withdrawn projects carried average interconnection costs of $599/kW, against $84/kW for recently completed projects; network upgrade costs averaged $563/kW for withdrawn projects and $71/kW for complete ones (Berkeley Lab, January 2023). The data show the association, not the reason for any single withdrawal, but they explain why an allocated-cost change is the first thing to examine at a decision point.
What to put in front of management
01
Cost exposure
Your allocated network upgrade costs now, what they were at the last decision point, and which upgrades are shared with other requests.
02
Dependency on others
Which of your results assume requests that could still withdraw, and what a restudy could move.
03
Money at risk
The deposit or security you must post to continue, and what you would forfeit or recover by withdrawing now under the governing tariff.
04
Schedule
The next phase's length, prior-cycle and affected-system dependencies, and the date that matters commercially.
05
Commercial path
Offtake, service type (energy-only or capacity) and whether the project still clears its investment case at the current cost.
06
Alternatives
Another point of interconnection, a smaller request, a later cycle, or a different service type, compared on the same basis.
Keep verified facts, project inputs, assumptions and unknowns separate, as in the interconnection due diligence checklist.
A decision rule
- Continue when the project still clears its investment case at the current allocated cost, the next deposit is justified by that case, and no unresolved unknown could reverse the answer before the following decision point.
- Review when an unknown could reverse the answer and can be resolved inside the decision window. Name the owner and the date.
- Withdraw or restructure when the case fails at the current cost, or when an unknown that could reverse it cannot be resolved before the money is committed. Check the tariff's penalty and refund terms first.
Node history can sharpen the questions. The public-record retrospectives show how earlier requests at specific points of interconnection resolved, without claiming why.
Facing a decision point on a live project?
Bring the decision, and get back a management-ready decision record: the cost and schedule evidence, the assumptions, the open unknowns, and whether to advance, review or withdraw.
Bring One Live DecisionSources
- FERC, Explainer on the Interconnection Final Rule (Order No. 2023)
- FERC, Explainer on Order No. 2023-A (March 21, 2024)
- PJM Manual 14H: New Service Requests Cycle Process, Revision 07 (effective August 19, 2026)
- SPP, Guidelines for the SPP GIP Process and Business Practices (effective February 1, 2025; revised May 2025)
- ISO New England, responses to Order No. 2023 process questions (January 18, 2024)
- Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition
- Lawrence Berkeley National Laboratory, “PJM data show substantial increases in interconnection costs” (January 19, 2023)
Sources checked September 17, 2026. Tariffs, manuals and queue rules change; the governing documents control any live project.
