Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue guide · SPP

SPP interconnection queue

How the DISIS cluster studies, the expedited ERAS round and the new Consolidated Planning Process fit together, and what the public queue record shows at individual points of interconnection.

GridVision AI ResearchPublished Updated

SPP at a glance

Cluster process
Definitive Interconnection System Impact Study (DISIS): an 11-month queue cluster window and a one-month review period, then Phase One, Decision Point 1, Phase Two and Decision Point 2.
Current DISIS cluster
DISIS-2024-001: 120 projects and 35,436 MW, with Phase Two in progress on SPP's schedule revised August 21, 2026.
Expedited Resource Adequacy Study (ERAS)
A one-time expedited study for projects nominated by load-responsible entities. ERAS-2025-001 lists 36 projects and 13,278 MW, with interconnection agreements in progress.
Consolidated Planning Process
Approved by FERC on March 13, 2026, effective March 1, 2026. SPP's first application window opened in April 2026 and is listed as open on the August 21, 2026 schedule.
Backlog
In September 2025, SPP reported 24 cluster studies completed since 2022, covering 1,652 projects and 340 GW of generation.
Study time
SPP says its average study time is already down to 18 months and anticipates about seven months under the new process, with full implementation beginning in 2027.

Sources: SPP Tariff Attachment V, Generator Interconnection Procedures; SPP Generator Interconnection study schedule, revised August 21, 2026; SPP news release, “SPP board approves expedited generation interconnection process,” May 8, 2025; SPP news release, “FERC approves SPP’s groundbreaking transmission planning proposal,” March 16, 2026; SPP news release, “Southwest Power Pool reaches milestone in acceleration of generation interconnection requests,” September 10, 2025; SPP news release, “SPP Consolidated Planning Process to reduce costs and help meet nation’s growing energy needs,” August 5, 2025.

Facts checked September 16, 2026.

How the SPP process works

SPP's DISIS cluster studies follow this sequence under Attachment V:

  1. 01DISIS queue cluster window11 calendar months.
  2. 02DISIS review periodOne calendar month.
  3. 03Phase OneWithin 60 calendar days after the review period closes.
  4. 04Decision Point 1
  5. 05Phase TwoWithin 120 calendar days after Decision Point 1 ends.
  6. 06Decision Point 2Followed by the remaining steps to an interconnection agreement.

Under the Consolidated Planning Process, SPP's Interconnection Cluster Study is due no later than 180 calendar days after its review period closes, followed by a 20-business-day decision point. The governing tariff controls any live project.

Sources: SPP Tariff Attachment V, Generator Interconnection Procedures; SPP compliance filing implementing the Consolidated Planning Process tariff revisions, April 13, 2026.

What the public record shows at SPP points of interconnection

Across the 11 SPP points of interconnection GridVision has published so far, the Berkeley Lab dataset records 111 interconnection requests filed between 2006 and 2025.

Outcomes of interconnection requests at the published SPP points of interconnection
OutcomeRequestsCapacity (MW)
Reached commercial operation162,162
Withdrew6714,238
Still active286,375
Total11122,775

For the requests that were built, the median time from request to commercial operation was 3.8 years. For those that withdrew, the median time from request to withdrawal was 0.9 years.

These 11 nodes are not a random sample of SPP, and a pattern at one point of interconnection does not transfer to another. The dataset records what happened, not why.

Published SPP point-of-interconnection retrospectives
Point of interconnectionStateRequestsBuiltWithdrawnActive
Carpenter 345 kV SubstationKansas9081
Setab 345 kV SubstationKansas12075
Minco 345 kVOklahoma16763
Riverside 345 kV SubstationOklahoma14059
Sweetwater 230 kVOklahoma5410
Woodward EHV 345 kVOklahoma5122
Beaver County 345 kV SubstationOklahoma / Texas9054
Chappelle Creek 345 kVSouth Dakota9180
Plant X 230 kV SubstationTexas150141
Tolk 230 kV SubstationTexas10073
TUCO 345 kVTexas7340

States with SPP requests

Requests at points of interconnection in these states are studied in the SPP queue. The count is how many of that state's requests the dataset places in this market; a state with requests in more than one market appears under each.

Questions to answer before advancing a SPP queue position

  • Which process is the project in (DISIS, ERAS or the Consolidated Planning Process), and which rules govern its next decision point?
  • What do your Phase One or Phase Two results assume about other requests in the same cluster?
  • What is at risk if you continue past the next decision point, and what is forfeited if you withdraw?
  • Which unknowns could change the answer, who owns each one, and when will it be resolved?

Weighing whether to advance a SPP queue position?

Bring the decision, and get back a management-ready decision record: what is verified, what is assumed, what is still unknown, and what to do next.

Request a qualification conversation

Sources

Facts checked September 16, 2026. Process rules and queue data change; the governing tariff, manuals and study documents control any live project.