Interconnection queue data
Iowa interconnection queue
506 interconnection requests have been filed at points of interconnection in Iowa since 2000, totalling 102 GW. Of that capacity, 12.2% reached commercial operation and 64.5% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 102 GW
- of capacity requested in Iowa since 2000
- 12.2%
- of it reached commercial operation; 64.5% withdrew
- 36 GW
- filed in the last six years (174 requests), of which 57.8% is still in the queue
Which markets Iowa requests sit in
A state is a location, not a market. Requests at Iowa points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| MISO | 480 | 97 GW | 12.7% | 63.0% | |
| West | 20 | 2 GW | 9.9% | 90.1% | |
| SPP | 4 | 341 MW | 0.0% | 21.7% | |
| PJM | 2 | 3 GW | 0.0% | 100.0% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Wind | 288 | 52 GW | 20.2% | 65.9% | |
| Solar | 64 | 9 GW | 1.6% | 45.7% | |
| Other | 53 | 15 GW | 1.6% | 90.0% | |
| Gas | 45 | 17 GW | 9.0% | 54.9% | |
| Battery | 40 | 6 GW | 0.0% | 40.6% | |
| Hybrid | 16 | 3 GW | 0.0% | 69.4% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 2000810 MW
- 20015 GW
- 20027 GW
- 20031 GW
- 2004352 MW
- 2005987 MW
- 20065 GW
- 20076 GW
- 20087 GW
- 20093 GW
- 20102 GW
- 20111 GW
- 201294 MW
- 20131 GW
- 20146 GW
- 20159 GW
- 20163 GW
- 20172 GW
- 20183 GW
- 20194 GW
- 20201 GW
- 20216 GW
- 202210 GW
- 2023211 MW
- 20246 GW
- 202513 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Killdeer4 requests in the dataset
- Mitchell County Substation4 requests in the dataset
- Duane Arnold (ARNOLD 5)4 requests in the dataset
- Denison4 requests in the dataset
- Franklin 161 kV Substation3 requests in the dataset
- Killdeer 345 kV Substation3 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.