Montana interconnection queue
531 interconnection requests have been filed at points of interconnection in Montana since 2000, totalling 51 GW. Of that capacity, 5.7% reached commercial operation and 64.2% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 51 GW
- of capacity requested in Montana since 2000
- 5.7%
- of it reached commercial operation; 64.2% withdrew
- 17 GW
- filed in the last six years (109 requests), of which 40.6% is still in the queue
Which markets Montana requests sit in
A state is a location, not a market. Requests at Montana points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| West | 507 | 48 GW | 5.9% | 63.1% | |
| SPP | 16 | 3 GW | 0.0% | 81.2% | |
| MISO | 8 | 499 MW | 23.4% | 76.6% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Wind | 219 | 27 GW | 6.6% | 59.5% | |
| Solar | 150 | 4 GW | 2.6% | 82.1% | |
| Other | 58 | 4 GW | 9.1% | 72.7% | |
| Hybrid | 47 | 8 GW | 2.2% | 56.8% | |
| Battery | 30 | 4 GW | 0.1% | 70.8% | |
| Gas | 27 | 4 GW | 10.5% | 77.9% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 2000400 MW
- 20011 GW
- 2002754 MW
- 2003764 MW
- 20041 GW
- 2005294 MW
- 2006910 MW
- 20072 GW
- 20084 GW
- 20092 GW
- 2010862 MW
- 2011690 MW
- 2012468 MW
- 2013781 MW
- 20141 GW
- 20151 GW
- 20162 GW
- 20173 GW
- 20183 GW
- 20196 GW
- 20205 GW
- 20212 GW
- 20226 GW
- 20232 GW
- 2024772 MW
- 2025735 MW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- 69kV line near Sumatra Substation12 requests in the dataset
- 100kV line between Loweth and Two Dot at Groveland.10 requests in the dataset
- Colstrip 500kV Substation7 requests in the dataset
- Yellowtail substation7 requests in the dataset
- Great Falls 230kV Switchyard6 requests in the dataset
- 69kV line East of Bole Substation5 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Want this reading for a Montana point of interconnection?
Send the node and the market. We read the public queue record for it — what was filed, what was built, what withdrew and how long each took — and send back what the record does and does not show.
Ask for a node retrospectivePublic-record reading only. Management review and formal interconnection studies remain authoritative.