Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Kansas interconnection queue

587 interconnection requests have been filed at points of interconnection in Kansas since 2001, totalling 124 GW. Of that capacity, 8.7% reached commercial operation and 65.0% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

124 GW
of capacity requested in Kansas since 2001
8.7%
of it reached commercial operation; 65.0% withdrew
55 GW
filed in the last six years (227 requests), of which 49.2% is still in the queue

Which markets Kansas requests sit in

A state is a location, not a market. Requests at Kansas points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
SPP585123 GW8.7%64.9%
MISO1135 MW0.0%100.0%
West1298 MW0.0%100.0%

Process pages: SPP, MISO.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Wind32465 GW14.4%74.0%
Solar12123 GW0.1%50.1%
Battery6310 GW0.0%44.2%
Gas4014 GW9.3%64.9%
Hybrid297 GW0.0%43.3%
Other104 GW1.2%94.4%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 20014 GW
  • 2002946 MW
  • 20032 GW
  • 20043 GW
  • 20051 GW
  • 20063 GW
  • 20074 GW
  • 20088 GW
  • 20095 GW
  • 20104 GW
  • 20115 GW
  • 20122 GW
  • 2013836 MW
  • 20141 GW
  • 20154 GW
  • 20165 GW
  • 201712 GW
  • 20183 GW
  • 20192 GW
  • 20205 GW
  • 20216 GW
  • 20225 GW
  • 202317 GW
  • 20244 GW
  • 202518 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Setab 345 kV Substation10 requests in the dataset
  • Carpenter 345 kV Substation9 requests in the dataset
  • Viola 345kV7 requests in the dataset
  • Swissvale 345kV7 requests in the dataset
  • Stranger Creek 345kV7 requests in the dataset
  • Post Rock - Spearville 345 kV6 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Published retrospectives in Kansas

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.