Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Minnesota interconnection queue

745 interconnection requests have been filed at points of interconnection in Minnesota since 2000, totalling 119 GW. Of that capacity, 8.2% reached commercial operation and 67.8% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

119 GW
of capacity requested in Minnesota since 2000
8.2%
of it reached commercial operation; 67.8% withdrew
41 GW
filed in the last six years (215 requests), of which 65.5% is still in the queue

Which markets Minnesota requests sit in

A state is a location, not a market. Requests at Minnesota points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
MISO735118 GW8.2%67.7%
West7436 MW7.1%92.9%
SPP3368 MW12.2%87.8%

Process pages: MISO, SPP.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Wind38956 GW9.4%82.3%
Solar15123 GW0.7%48.7%
Battery7212 GW0.0%38.0%
Gas5618 GW19.6%72.6%
Other555 GW12.7%86.4%
Hybrid224 GW0.2%23.7%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2000562 MW
  • 20012 GW
  • 200210 GW
  • 20034 GW
  • 20043 GW
  • 20051 GW
  • 20063 GW
  • 200722 GW
  • 20086 GW
  • 20093 GW
  • 20103 GW
  • 20111 GW
  • 2012276 MW
  • 20131 GW
  • 20142 GW
  • 20151 GW
  • 20164 GW
  • 20173 GW
  • 20184 GW
  • 20193 GW
  • 20202 GW
  • 20213 GW
  • 20229 GW
  • 2023118 MW
  • 202412 GW
  • 202515 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Cedar Mountain - Lyon County 345.0kV8 requests in the dataset
  • Pleasant Valley 345 kV Substation5 requests in the dataset
  • ALEXANDRIA - BISON 345.0kV5 requests in the dataset
  • Chanarambie Substation4 requests in the dataset
  • Benton County 115kV Substation3 requests in the dataset
  • Chanarambie 115kV3 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.