Minco 345 kV: interconnection queue history

Seven of sixteen requests reached commercial operation.

GridVision AI ResearchUpdated

Sixteen interconnection requests since 2007: 7 reached commercial operation, 6 withdrew, and 3 remain active.

Built
7
Withdrawn
6
Still in queue
3

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2007-10-02(unnamed)Wind200 MWBuilt2010-11-01 · 3.1 yrs
2011-03-30(unnamed)Wind100.8 MWBuilt2012-10-01 · 1.5 yrs
2014-02-19(unnamed)Wind5.7 MWBuilt2015-06-01 · 1.3 yrs
2014-09-29(unnamed)Wind250 MWBuilt2018-12-22 · 4.2 yrs
2015-10-05(unnamed)Battery20 MWWithdrawn2016-03-17
2015-10-06(unnamed)Wind6.3 MWWithdrawn2016-08-29
2015-10-06(unnamed)Wind100 MWBuilt2018-12-22 · 3.2 yrs
2016-11-30(unnamed)Wind2.5 MWBuilt2021-10-25 · 4.9 yrs
2017-05-30(unnamed)Solar200.25 MWWithdrawn2020-12-07
2017-11-28(unnamed)Wind215 MWStill in queue
2017-11-28(unnamed)Solar250 MWStill in queue
2022-05-23(unnamed)Battery85 MWWithdrawn2022-11-03
2022-11-30(unnamed)Battery85 MWWithdrawn2023-10-26
2023-06-20(unnamed)Battery80 MWBuilt2025-04-15 · 1.8 yrs
2025-03-01(unnamed)Battery190 MWWithdrawn2025-12-05
2025-06-04(unnamed)Battery200 MWStill in queue

What the record shows

  • 587 MW of the 1,991 MW filed here withdrew, and 739 MW reached commercial operation.
  • Completions here took between 1.3 and 4.9 years from request to commercial operation (median 3.1).
  • The largest request filed here, 250 MW (solar), was filed in 2017 and is still active.
  • Two requests were filed on 2017-11-28; all of them remain active.
  • Five of the 6 withdrawals came within a year of filing.
  • By technology, the requests here were wind 8, battery 6, solar 2.
  • The longest-standing active request here was filed on 2017-11-28.
  • The dataset records this point of interconnection under five spellings, which are combined here.

What a decision record would have to make explicit

  • What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
  • Three requests are unresolved, so the outcome counts at this node can still change.
  • The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.