Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

North Dakota interconnection queue

410 interconnection requests have been filed at points of interconnection in North Dakota since 2000, totalling 75 GW. Of that capacity, 7.5% reached commercial operation and 73.2% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

75 GW
of capacity requested in North Dakota since 2000
7.5%
of it reached commercial operation; 73.2% withdrew
27 GW
filed in the last six years (115 requests), of which 40.7% is still in the queue

Which markets North Dakota requests sit in

A state is a location, not a market. Requests at North Dakota points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
MISO23741 GW7.8%76.1%
West8714 GW9.4%82.7%
SPP8519 GW5.9%57.3%
PJM12 GW0.0%100.0%

Process pages: MISO, SPP, PJM.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Wind26545 GW9.5%78.4%
Solar418 GW0.0%80.8%
Other337 GW10.0%77.0%
Gas338 GW8.8%50.4%
Battery285 GW0.0%54.1%
Hybrid103 GW0.0%57.7%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 2000132 MW
  • 20013 GW
  • 20022 GW
  • 20031 GW
  • 2004191 MW
  • 20051 GW
  • 20062 GW
  • 20077 GW
  • 20085 GW
  • 20094 GW
  • 2010657 MW
  • 20112 GW
  • 20121 GW
  • 20131 GW
  • 20143 GW
  • 20153 GW
  • 20164 GW
  • 20173 GW
  • 20182 GW
  • 20192 GW
  • 20202 GW
  • 20215 GW
  • 20227 GW
  • 20234 GW
  • 20243 GW
  • 20257 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Maple River 230 kV Substation13 requests in the dataset
  • Williston 115kV7 requests in the dataset
  • AVS-Broadland 345kV7 requests in the dataset
  • Langdon 115 kV Substation5 requests in the dataset
  • Logan 230kV Substation5 requests in the dataset
  • Leland Olds-Groton 345kV5 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.