SPP · Texas · Public-record retrospective
Plant X 230 kV Substation: interconnection queue history
Fourteen of fifteen requests withdrew; one is still in the queue.
GridVision AI ResearchUpdated
Fifteen interconnection requests since 2017: 14 withdrew and 1 remains active.
- Built
- 0
- Withdrawn
- 14
- Still in queue
- 1
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2017-11-30 | (unnamed) | Solar | 300 MW | Withdrawn2022-10-13 |
| 2018-11-18 | (unnamed) | Solar | 175 MW | Withdrawn2023-09-28 |
| 2019-05-24 | (unnamed) | Battery | 100 MW | Withdrawn2023-09-28 |
| 2022-06-23 | (unnamed) | Solar | 300 MW | Withdrawn2023-11-06 |
| 2023-09-25 | (unnamed) | Solar | 256 MW | Withdrawn2025-08-25 |
| 2023-10-02 | (unnamed) | Battery | 200 MW | Withdrawn2025-08-25 |
| 2023-10-02 | (unnamed) | Solar | 250 MW | Withdrawn2023-11-27 |
| 2023-10-02 | (unnamed) | Solar | 250 MW | Withdrawn2023-11-27 |
| 2023-10-02 | (unnamed) | Solar | 250 MW | Withdrawn2023-11-27 |
| 2023-10-02 | (unnamed) | Solar | 250 MW | Withdrawn2023-11-27 |
| 2023-10-02 | (unnamed) | Solar | 256 MW | Withdrawn2025-08-25 |
| 2023-10-02 | (unnamed) | Solar | 275 MW | Withdrawn2025-08-25 |
| 2023-10-02 | (unnamed) | Wind | 300 MW | Withdrawn2025-08-25 |
| 2024-10-30 | (unnamed) | Solar | 256 MW | Still in queue |
| 2025-03-01 | (unnamed) | Solar | 200 MW | Withdrawn2025-08-28 |
What the record shows
- 3,362 MW of the 3,618 MW filed here withdrew.
- The largest request filed here, 300 MW (wind), withdrew 1.9 years after filing.
- Eight requests were filed on 2023-10-02; all of them withdrew.
- Five of the 14 withdrawals came within a year of filing.
- By technology, the requests here were solar 12, battery 2, wind 1.
- The longest-standing active request here was filed on 2024-10-30.
- The dataset records this point of interconnection under two spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- One request is unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- SPP · TexasTUCO 345 kV7 requests · 3 built · 4 withdrawn · 0 still in queueRead the record
- SPP · TexasTolk 230 kV Substation10 requests · 0 built · 7 withdrawn · 3 still in queueRead the record
- SPP · OklahomaSweetwater 230 kV5 requests · 4 built · 1 withdrawn · 0 still in queueRead the record
- SPP · OklahomaWoodward EHV 345 kV5 requests · 1 built · 2 withdrawn · 2 still in queueRead the record
How the SPP process works today: SPP interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.