Interconnection queue data
Texas interconnection queue
3,302 interconnection requests have been filed at points of interconnection in Texas since 2000, totalling 711 GW. Of that capacity, 8.3% reached commercial operation and 25.1% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 711 GW
- of capacity requested in Texas since 2000
- 8.3%
- of it reached commercial operation; 25.1% withdrew
- 529 GW
- filed in the last six years (2,379 requests), of which 82.0% is still in the queue
Which markets Texas requests sit in
A state is a location, not a market. Requests at Texas points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| ERCOT | 2,764 | 587 GW | 9.0% | 15.3% | |
| SPP | 420 | 96 GW | 5.0% | 73.5% | |
| MISO | 100 | 24 GW | 5.2% | 66.8% | |
| West | 18 | 4 GW | 9.6% | 45.8% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 915 | 193 GW | 10.2% | 35.5% | |
| Battery | 833 | 153 GW | 1.9% | 8.6% | |
| Hybrid | 592 | 128 GW | 2.6% | 2.6% | |
| Wind | 496 | 123 GW | 14.2% | 40.3% | |
| Gas | 235 | 84 GW | 8.3% | 30.6% | |
| Other | 231 | 30 GW | 29.6% | 60.0% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 2000280 MW
- 2001600 MW
- 20022 GW
- 20031 GW
- 2004910 MW
- 20051 GW
- 20063 GW
- 20073 GW
- 200810 GW
- 20095 GW
- 20104 GW
- 20113 GW
- 20123 GW
- 20135 GW
- 20148 GW
- 201513 GW
- 201612 GW
- 201728 GW
- 201836 GW
- 201942 GW
- 202047 GW
- 202160 GW
- 202278 GW
- 2023104 GW
- 2024119 GW
- 2025121 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Hillje 345kV10 requests in the dataset
- Plant X 230kV Substation9 requests in the dataset
- Mustang 230kV8 requests in the dataset
- Hitchland 345kV7 requests in the dataset
- TUCO 345kV7 requests in the dataset
- Potter 345kV Substation7 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Published retrospectives in Texas
- TUCO 345 kV (SPP)
- Plant X 230 kV Substation (SPP)
- Tolk 230 kV Substation (SPP)
- Beaver County 345 kV Substation (SPP)
- Hillje 345 kV (ERCOT)
- Schneeman Draw 345 kV (ERCOT)
- Tesla 345 kV (ERCOT)
- Bakersfield 345 kV (ERCOT)
- Cenizo 345 kV (ERCOT)
- Long Draw 138 kV (ERCOT)
- Sam Switch 345 kV (ERCOT)
- Amos Cr 345 kV (ERCOT)
- Asherton 138 kV (ERCOT)
- Clear Crossing 345 kV (ERCOT)
- Divide 345 kV (ERCOT)
- King Mt 138 kV (ERCOT)
- Lamesa 138 kV (ERCOT)
- Pomelo 345 kV (ERCOT)
- Krum 345 kV (ERCOT)
- Peters 138 kV (ERCOT)
- Pinto Creek 138 kV (ERCOT)
- Twin Buttes 345 kV (ERCOT)
- White River 345 kV (ERCOT)
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.