ERCOT · Texas · Public-record retrospective
Krum 345 kV: interconnection queue history
Two of three requests reached commercial operation.
GridVision AI ResearchUpdated
Three interconnection requests since 2018: 2 reached commercial operation and 1 withdrew.
- Built
- 2
- Withdrawn
- 1
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2018-08-20 | R-Cube Wind | Wind | 1000 MW | Withdrawn2019-02-04 |
| 2018-11-05 | Noble Solar | Solar | 279 MW | Built2022-09-19 · 3.9 yrs |
| 2020-05-19 | Hummingbird Storage | Other | 103.8 MW | Built2024-06-24 · 4.1 yrs |
What the record shows
- 1,000 MW of the 1,383 MW filed here withdrew, and 383 MW reached commercial operation.
- Completions here took between 3.9 and 4.1 years from request to commercial operation (median 4.0).
- The largest request filed here, 1,000 MW (wind), withdrew 0.5 years after filing.
- By technology, the requests here were other 1, solar 1, wind 1.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- ERCOT · TexasHillje 345 kV10 requests · 2 built · 4 withdrawn · 4 still in queueRead the record
- ERCOT · TexasSchneeman Draw 345 kV8 requests · 4 built · 4 withdrawn · 0 still in queueRead the record
- ERCOT · TexasTesla 345 kV8 requests · 1 built · 3 withdrawn · 4 still in queueRead the record
- ERCOT · TexasBakersfield 345 kV7 requests · 4 built · 3 withdrawn · 0 still in queueRead the record
How the ERCOT process works today: ERCOT interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.