ERCOT interconnection queue

How ERCOT's generation interconnection studies work, what a developer files and when, and what the public record shows for Texas requests.

GridVision AI ResearchPublished Updated

ERCOT at a glance

Rulebook
ERCOT is not FERC-jurisdictional. Generation interconnection follows ERCOT Planning Guide Section 5 and the Nodal Operating Guide, under Public Utility Commission of Texas oversight.
Studies
Planning Guide Section 5.3 names the security screening study (5.3.1), the full interconnection study (5.3.2), the ERCOT economic study (5.3.3), the reactive study (5.3.4) and the quarterly stability assessment (5.3.5).
What you file
An interconnection request through the RIOO-IS application, with separate paths under and over 10 MW; resource asset registration forms for transmission-connected resources; dynamic model templates with model quality test reports under Planning Guide 6.2(5); and a battery request-for-information template for projects with storage.
Agreement
The standard generation interconnection agreement dated November 6, 2025 took effect on January 1, 2026.
Network upgrades
Trade press describes ERCOT's approach as connect and manage: studies focus on the local upgrades needed to connect, and congestion is handled through redispatch and curtailment rather than assigning broad network upgrade costs to the generator.
Public record
ERCOT publishes a monthly generation interconnection status report, and since March 2026 a companion transmission interconnection costs report covering transmission-level generators energized in the previous month.

Sources: ERCOT Planning Guide, Section 5 (July 1, 2026); ERCOT, Resource Integration; ERCOT, Resource Adequacy (Generation Interconnection Status report); Utility Dive, “Can ERCOT show the way to faster and cheaper grid interconnection?” (trade press).

Facts checked September 18, 2026.

How the ERCOT process works

ERCOT's Planning Guide sets the generation interconnection sequence:

  1. 01Submit the interconnection requestFiled through RIOO-IS; Planning Guide Section 5.1.1 sets which projects and modifications use this process.
  2. 02Security screening studyPlanning Guide Section 5.3.1.
  3. 03Full interconnection studyPlanning Guide Section 5.3.2, with proof of site control (5.3.2.1) and a study scoping process (5.3.2.2); it covers steady state, short circuit, dynamics and facilities.
  4. 04Reactive study and quarterly stability assessmentPlanning Guide Sections 5.3.4 and 5.3.5.
  5. 05Registration and modellingResource asset registration forms, dynamic models and model quality test reports.
  6. 06Interconnection agreement, commissioning and energizationUnder the standard generation interconnection agreement effective January 1, 2026.

Section numbers are from the July 1, 2026 Planning Guide; ERCOT revises it on a rolling schedule, and the current version governs any live project. Large loads of 75 MW or more follow a separate ERCOT process.

Sources: ERCOT Planning Guide, Section 5 (July 1, 2026); ERCOT, Resource Integration; ERCOT, Large Load Integration.

What the public record shows at ERCOT points of interconnection

Across the 19 ERCOT points of interconnection GridVision has published so far, the Berkeley Lab dataset records 92 interconnection requests filed between 2013 and 2025.

Outcomes of interconnection requests at the published ERCOT points of interconnection
OutcomeRequestsCapacity (MW)
Reached commercial operation427,838
Withdrew3510,029
Still active153,713
Total9221,579

For the requests that were built, the median time from request to commercial operation was 4.1 years. For those that withdrew, the median time from request to withdrawal was 2.6 years.

These 19 nodes are not a random sample of ERCOT, and a pattern at one point of interconnection does not transfer to another. The dataset records what happened, not why.

Published ERCOT point-of-interconnection retrospectives
Point of interconnectionStateRequestsBuiltWithdrawnActive
Amos Cr 345 kVTexas4400
Asherton 138 kVTexas4121
Bakersfield 345 kVTexas7430
Cenizo 345 kVTexas6132
Clear Crossing 345 kVTexas4220
Divide 345 kVTexas4301
Hillje 345 kVTexas10244
King Mt 138 kVTexas4130
Krum 345 kVTexas3210
Lamesa 138 kVTexas4310
Long Draw 138 kVTexas5320
Peters 138 kVTexas3120
Pinto Creek 138 kVTexas3210
Pomelo 345 kVTexas4121
Sam Switch 345 kVTexas5212
Schneeman Draw 345 kVTexas8440
Tesla 345 kVTexas8134
Twin Buttes 345 kVTexas3300
White River 345 kVTexas3210

Questions to answer before advancing a ERCOT queue position

  • Which study is the project waiting on, and what would change its result?
  • If congestion is managed by curtailment rather than by upgrades, what curtailment does the revenue case assume?
  • What does the site control evidence have to show before the full interconnection study?
  • Which unknowns could change the answer, who owns each one, and when will it be resolved?

Weighing whether to advance a ERCOT queue position?

Bring the decision, and get back a management-ready decision record: what is verified, what is assumed, what is still unknown, and what to do next.

Bring One Live Decision

Sources

Facts checked September 18, 2026. Process rules and queue data change; the governing tariff, manuals and study documents control any live project.