ERCOT · Texas · Public-record retrospective
Long Draw 138 kV: interconnection queue history
Three of five requests reached commercial operation.
GridVision AI ResearchUpdated
Five interconnection requests since 2016: 3 reached commercial operation and 2 withdrew.
- Built
- 3
- Withdrawn
- 2
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2016-12-14 | Long Draw Solar | Solar | 226.73 MW | Built2021-12-14 · 5.0 yrs |
| 2018-08-13 | Juno Solar (Phase I) | Solar | 166.12 MW | Built2021-05-26 · 2.8 yrs |
| 2018-08-13 | Juno Storage | Other | 495 MW | Withdrawn2019-06-10 |
| 2022-05-09 | BoCo BESS | Other | 155.48 MW | Built2024-08-12 · 2.3 yrs |
| 2022-11-14 | JUNO BESS | Other | 355.21 MW | Withdrawn2023-08-17 |
What the record shows
- 850 MW of the 1,399 MW filed here withdrew, and 548 MW reached commercial operation.
- Completions here took between 2.3 and 5.0 years from request to commercial operation (median 2.8).
- The largest request filed here, 495 MW (other), withdrew 0.8 years after filing.
- Two requests were filed on 2018-08-13; 1 reached operation and 1 withdrew.
- Two of the 2 withdrawals came within a year of filing.
- By technology, the requests here were other 3, solar 2.
- The dataset records this point of interconnection under two spellings, which are combined here.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- ERCOT · TexasHillje 345 kV10 requests · 2 built · 4 withdrawn · 4 still in queueRead the record
- ERCOT · TexasSchneeman Draw 345 kV8 requests · 4 built · 4 withdrawn · 0 still in queueRead the record
- ERCOT · TexasTesla 345 kV8 requests · 1 built · 3 withdrawn · 4 still in queueRead the record
- ERCOT · TexasBakersfield 345 kV7 requests · 4 built · 3 withdrawn · 0 still in queueRead the record
How the ERCOT process works today: ERCOT interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.