ERCOT · Texas · Public-record retrospective
Twin Buttes 345 kV: interconnection queue history
All three requests filed here reached commercial operation.
GridVision AI ResearchUpdated
Three interconnection requests since 2017: 3 reached commercial operation.
- Built
- 3
- Withdrawn
- 0
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2017-08-08 | Rambler Solar | Solar | 200 MW | Built2020-10-01 · 3.1 yrs |
| 2018-11-19 | Angelo Solar | Solar | 195.41 MW | Built2024-03-25 · 5.3 yrs |
| 2021-11-21 | Angelo Storage | Other | 102.97 MW | Built2024-03-25 · 2.3 yrs |
What the record shows
- 498 MW of the 498 MW filed here reached commercial operation.
- Completions here took between 2.3 and 5.3 years from request to commercial operation (median 3.1).
- The largest request filed here, 200 MW (solar), reached operation 3.1 years after filing.
- By technology, the requests here were solar 2, other 1.
What a decision record would have to make explicit
- Every request at this node reached operation. That describes past outcomes, not the capacity available at this node today.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- ERCOT · TexasHillje 345 kV10 requests · 2 built · 4 withdrawn · 4 still in queueRead the record
- ERCOT · TexasSchneeman Draw 345 kV8 requests · 4 built · 4 withdrawn · 0 still in queueRead the record
- ERCOT · TexasTesla 345 kV8 requests · 1 built · 3 withdrawn · 4 still in queueRead the record
- ERCOT · TexasBakersfield 345 kV7 requests · 4 built · 3 withdrawn · 0 still in queueRead the record
How the ERCOT process works today: ERCOT interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.
