Interconnection queue data
Nebraska interconnection queue
388 interconnection requests have been filed at points of interconnection in Nebraska since 2001, totalling 68 GW. Of that capacity, 8.1% reached commercial operation and 67.5% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 68 GW
- of capacity requested in Nebraska since 2001
- 8.1%
- of it reached commercial operation; 67.5% withdrew
- 28 GW
- filed in the last six years (145 requests), of which 44.4% is still in the queue
Which markets Nebraska requests sit in
A state is a location, not a market. Requests at Nebraska points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| SPP | 369 | 61 GW | 8.4% | 65.0% | |
| West | 18 | 7 GW | 6.0% | 89.6% | |
| MISO | 1 | 46 MW | 0.0% | 100.0% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Wind | 200 | 34 GW | 10.2% | 83.3% | |
| Solar | 63 | 13 GW | 0.6% | 62.2% | |
| Gas | 49 | 9 GW | 11.0% | 28.9% | |
| Battery | 32 | 4 GW | 0.0% | 41.8% | |
| Other | 26 | 4 GW | 21.2% | 66.8% | |
| Hybrid | 18 | 3 GW | 0.0% | 64.3% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 2001951 MW
- 2002481 MW
- 2003875 MW
- 2004381 MW
- 200550 MW
- 20063 GW
- 20073 GW
- 20082 GW
- 2009160 MW
- 20101 GW
- 2011400 MW
- 2012484 MW
- 20132 GW
- 20141 GW
- 20152 GW
- 20164 GW
- 20174 GW
- 201811 GW
- 20193 GW
- 20206 GW
- 20214 GW
- 20222 GW
- 20238 GW
- 20243 GW
- 20255 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Substation 3740 345 kV6 requests in the dataset
- New Beatrice Power Station 345 kV5 requests in the dataset
- Olive Creek 345 kV Substation5 requests in the dataset
- Broken Bow 115kV4 requests in the dataset
- Meadow Grove 230kV4 requests in the dataset
- Hoskins 345kV4 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.