Interconnection queue data

New Mexico interconnection queue

622 interconnection requests have been filed at points of interconnection in New Mexico since 2001, totalling 96 GW. Of that capacity, 6.0% reached commercial operation and 60.5% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

96 GW
of capacity requested in New Mexico since 2001
6.0%
of it reached commercial operation; 60.5% withdrew
52 GW
filed in the last six years (344 requests), of which 46.3% is still in the queue

Which markets New Mexico requests sit in

A state is a location, not a market. Requests at New Mexico points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
West41753 GW7.3%51.5%
SPP20441 GW4.5%70.6%
CAISO12 GW0.0%100.0%

Process pages: SPP, CAISO.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar29220 GW5.3%75.0%
Hybrid14630 GW2.7%54.3%
Wind8626 GW11.0%61.7%
Battery6210 GW0.0%37.0%
Gas237 GW14.4%62.6%
Other134 GW0.4%85.7%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 20012 GW
  • 200250 MW
  • 2003378 MW
  • 20041 GW
  • 2005410 MW
  • 20062 GW
  • 20073 GW
  • 20083 GW
  • 2009266 MW
  • 20101 GW
  • 20112 GW
  • 2012992 MW
  • 20132 GW
  • 20142 GW
  • 20152 GW
  • 20163 GW
  • 20175 GW
  • 20183 GW
  • 201910 GW
  • 20206 GW
  • 20216 GW
  • 20226 GW
  • 202312 GW
  • 20243 GW
  • 202520 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Hondale Substation Distribution Feeder 119 requests in the dataset
  • Hermanas Substation Distribution Feeder 119 requests in the dataset
  • Four Corners 230kV substation6 requests in the dataset
  • Gold Substation Distribution Feeder 116 requests in the dataset
  • Lordsburg Substation Distribution Feeder 3186 requests in the dataset
  • Eddy County-Tolk (Crossroads) 345kV6 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Want this reading for a New Mexico point of interconnection?

Send the node and the market. We read the public queue record for it — what was filed, what was built, what withdrew and how long each took — and send back what the record does and does not show.

Ask for a node retrospective

Public-record reading only. Management review and formal interconnection studies remain authoritative.