Interconnection queue data
Ohio interconnection queue
906 interconnection requests have been filed at points of interconnection in Ohio since 2001, totalling 112 GW. Of that capacity, 13.5% reached commercial operation and 68.8% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 112 GW
- of capacity requested in Ohio since 2001
- 13.5%
- of it reached commercial operation; 68.8% withdrew
- 35 GW
- filed in the last six years (362 requests), of which 35.7% is still in the queue
Which markets Ohio requests sit in
A state is a location, not a market. Requests at Ohio points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| PJM | 866 | 105 GW | 13.2% | 68.1% | |
| MISO | 40 | 7 GW | 18.3% | 79.6% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 451 | 37 GW | 11.5% | 56.9% | |
| Other | 102 | 15 GW | 11.8% | 88.0% | |
| Wind | 100 | 17 GW | 6.4% | 89.8% | |
| Battery | 99 | 8 GW | 0.6% | 77.0% | |
| Gas | 96 | 30 GW | 26.6% | 61.6% | |
| Hybrid | 58 | 5 GW | 0.1% | 57.8% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20012 GW
- 20022 GW
- 2003165 MW
- 20041 GW
- 20053 GW
- 20063 GW
- 20076 GW
- 20084 GW
- 20093 GW
- 20105 GW
- 20113 GW
- 20124 GW
- 20132 GW
- 20142 GW
- 20153 GW
- 201610 GW
- 20178 GW
- 20187 GW
- 20199 GW
- 202010 GW
- 202111 GW
- 20226 GW
- 20232 GW
- 20256 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Marysville-Flatlick 765 kV7 requests in the dataset
- Hillsboro 138kV6 requests in the dataset
- Buckskin 69kV6 requests in the dataset
- Tait 69kV5 requests in the dataset
- East Lima-Marysville 345kV4 requests in the dataset
- Hardin Switch 345 kV4 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Published retrospectives in Ohio
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.