Interconnection queue data
Kentucky interconnection queue
483 interconnection requests have been filed at points of interconnection in Kentucky since 2000, totalling 88 GW. Of that capacity, 4.6% reached commercial operation and 71.1% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 88 GW
- of capacity requested in Kentucky since 2000
- 4.6%
- of it reached commercial operation; 71.1% withdrew
- 41 GW
- filed in the last six years (280 requests), of which 39.3% is still in the queue
Which markets Kentucky requests sit in
A state is a location, not a market. Requests at Kentucky points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| PJM | 213 | 25 GW | 1.1% | 70.7% | |
| Southeast | 190 | 48 GW | 4.3% | 73.4% | |
| MISO | 80 | 15 GW | 11.1% | 64.3% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 261 | 30 GW | 0.7% | 69.7% | |
| Hybrid | 69 | 10 GW | 0.0% | 73.4% | |
| Other | 58 | 21 GW | 8.1% | 90.0% | |
| Gas | 49 | 21 GW | 10.3% | 52.7% | |
| Battery | 40 | 6 GW | 0.0% | 69.1% | |
| Wind | 6 | 860 MW | 0.0% | 76.7% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20006 GW
- 20015 GW
- 2002750 MW
- 20052 GW
- 2006485 MW
- 20074 GW
- 2008154 MW
- 20092 GW
- 20103 GW
- 20111 GW
- 2012238 MW
- 20133 GW
- 2014218 MW
- 20151 GW
- 20161 GW
- 2017511 MW
- 20182 GW
- 20199 GW
- 20205 GW
- 202113 GW
- 202210 GW
- 20232 GW
- 20245 GW
- 20255 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Green River substation on the 161 kV side6 requests in the dataset
- Inez 138 kV5 requests in the dataset
- Millersburg 69 kV5 requests in the dataset
- AB Brown 345 - Reid EHV (BREC Terminal) 345.0kV4 requests in the dataset
- Engle 69kV4 requests in the dataset
- Brown North Substation 345 kV bus.3 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Want this reading for a Kentucky point of interconnection?
Send the node and the market. We read the public queue record for it — what was filed, what was built, what withdrew and how long each took — and send back what the record does and does not show.
Ask for a node retrospectivePublic-record reading only. Management review and formal interconnection studies remain authoritative.