Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Illinois interconnection queue

1,219 interconnection requests have been filed at points of interconnection in Illinois since 2000, totalling 206 GW. Of that capacity, 8.2% reached commercial operation and 55.7% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

206 GW
of capacity requested in Illinois since 2000
8.2%
of it reached commercial operation; 55.7% withdrew
103 GW
filed in the last six years (619 requests), of which 59.4% is still in the queue

Which markets Illinois requests sit in

A state is a location, not a market. Requests at Illinois points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
MISO610117 GW5.7%49.3%
PJM60989 GW11.4%64.1%

Process pages: MISO, PJM.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Solar38955 GW2.3%45.0%
Wind36463 GW12.0%63.6%
Battery21429 GW0.3%42.6%
Hybrid9116 GW0.0%32.8%
Other8319 GW13.6%81.5%
Gas7823 GW22.6%69.6%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 20001 GW
  • 20014 GW
  • 2002829 MW
  • 20032 GW
  • 20043 GW
  • 20057 GW
  • 20066 GW
  • 20077 GW
  • 20085 GW
  • 20094 GW
  • 20104 GW
  • 20111 GW
  • 20124 GW
  • 2013782 MW
  • 20148 GW
  • 20155 GW
  • 20167 GW
  • 20176 GW
  • 201816 GW
  • 201910 GW
  • 202015 GW
  • 20218 GW
  • 202237 GW
  • 20232 GW
  • 202424 GW
  • 202517 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • Nelson-Electric Junction 345 kV7 requests in the dataset
  • 7FARGO - 7SANDBURG 345.0kV6 requests in the dataset
  • Blue Mound-Chestnut 345 kV6 requests in the dataset
  • 7CASEY - 7NEWTON 345.0kV5 requests in the dataset
  • Powerton-Nevada 345 kV5 requests in the dataset
  • Rising4 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Published retrospectives in Illinois

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.