Interconnection queue data
Indiana interconnection queue
943 interconnection requests have been filed at points of interconnection in Indiana since 2000, totalling 184 GW. Of that capacity, 6.1% reached commercial operation and 61.4% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 184 GW
- of capacity requested in Indiana since 2000
- 6.1%
- of it reached commercial operation; 61.4% withdrew
- 101 GW
- filed in the last six years (577 requests), of which 47.4% is still in the queue
Which markets Indiana requests sit in
A state is a location, not a market. Requests at Indiana points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| MISO | 583 | 120 GW | 5.8% | 59.5% | |
| PJM | 356 | 60 GW | 7.2% | 63.9% | |
| Southeast | 4 | 3 GW | 0.0% | 83.9% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 383 | 59 GW | 3.0% | 57.4% | |
| Battery | 180 | 24 GW | 0.1% | 56.7% | |
| Wind | 167 | 37 GW | 10.5% | 80.0% | |
| Hybrid | 116 | 23 GW | 2.6% | 54.7% | |
| Gas | 55 | 31 GW | 12.4% | 46.2% | |
| Other | 42 | 11 GW | 11.9% | 88.1% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20004 GW
- 20012 GW
- 200283 MW
- 2003440 MW
- 20042 GW
- 2005750 MW
- 20062 GW
- 20075 GW
- 20086 GW
- 20095 GW
- 20101 GW
- 20116 GW
- 20124 GW
- 20132 GW
- 20141 GW
- 20153 GW
- 20165 GW
- 20177 GW
- 20189 GW
- 201914 GW
- 202019 GW
- 202113 GW
- 202230 GW
- 20231 GW
- 202417 GW
- 202521 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Jay 138 kV8 requests in the dataset
- Edwardsport IGCC - Amo 345.0kV7 requests in the dataset
- Sorenson 345 kV7 requests in the dataset
- Olive-Dequine 345kV7 requests in the dataset
- Schahfer - Burr Oak 345kV Line6 requests in the dataset
- Gibson Sta - Merom (HED) 345.0kV6 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Published retrospectives in Indiana
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.