MISO · Indiana · Public-record retrospective
Reynolds 345 kV Substation: interconnection queue history
Four of nine requests reached commercial operation.
GridVision AI ResearchUpdated
Nine interconnection requests since 2017: 4 reached commercial operation, 2 withdrew, and 3 remain active.
- Built
- 4
- Withdrawn
- 2
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2017-06-16 | (unnamed) | Solar | 200 MW | Built2022-08-15 · 5.2 yrs |
| 2017-06-16 | (unnamed) | Wind | 200.1 MW | Built2021-08-15 · 4.2 yrs |
| 2017-06-16 | (unnamed) | Wind | 200.1 MW | Built2021-08-15 · 4.2 yrs |
| 2018-03-12 | (unnamed) | Wind | 200 MW | Still in queue |
| 2018-03-12 | (unnamed) | Wind | 200 MW | Built2023-04-20 · 5.1 yrs |
| 2020-06-22 | (unnamed) | Solar | 200 MW | Still in queue |
| 2020-06-23 | (unnamed) | Wind | 200 MW | Withdrawn2020-12-18 |
| 2020-11-06 | Surplus; J913 | Storage | 200 MW | Withdrawn2021-02-10 |
| 2022-09-13 | (unnamed) | Battery | 400 MW | Still in queue |
What the record shows
- 400 MW of the 2,000 MW filed here withdrew, and 800 MW reached commercial operation.
- Completions here took between 4.2 and 5.2 years from request to commercial operation (median 4.6).
- The largest request filed here, 400 MW (battery), was filed in 2022 and is still active.
- Three requests were filed on 2017-06-16; all of them reached operation.
- Two of the 2 withdrawals came within a year of filing.
- By technology, the requests here were wind 5, solar 2, battery 1, storage 1.
- The longest-standing active request here was filed on 2018-03-12.
- The dataset records this point of interconnection under four spellings, which are combined here.
What a decision record would have to make explicit
- What separated the requests that reached operation from those that withdrew, such as study results, upgrade assignments or site conditions, is not in the public queue record, so a decision record here would have to carry it as an unknown.
- Three requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- MISO · ArkansasSheridan EHV - El Dorado EHV 500 kV10 requests · 0 built · 7 withdrawn · 3 still in queueRead the record
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- PJM · PennsylvaniaHatfield 500 kV6 requests · 3 built · 3 withdrawn · 0 still in queueRead the record
How the MISO process works today: MISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.