MISO · Arkansas · Public-record retrospective
Sheridan EHV - El Dorado EHV 500 kV: interconnection queue history
Seven of ten requests withdrew; three are still in the queue.
GridVision AI ResearchUpdated
Ten interconnection requests since 2022: 7 withdrew and 3 remain active.
- Built
- 0
- Withdrawn
- 7
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2022-09-14 | (unnamed) | Solar | 500 MW | Still in queue |
| 2022-09-15 | (unnamed) | Solar + battery | 160 MW | Still in queue |
| 2022-09-15 | (unnamed) | Solar | 394.5 MW | Withdrawn2025-07-30 |
| 2022-09-15 | (unnamed) | Solar | 400 MW | Still in queue |
| 2022-09-15 | (unnamed) | Solar | 500 MW | Withdrawn2025-07-31 |
| 2024-04-16 | (unnamed) | Solar | 400 MW | Withdrawn2025-12-23 |
| 2024-04-18 | (unnamed) | Battery | 200 MW | Withdrawn2025-05-09 |
| 2024-04-18 | (unnamed) | Solar | 400 MW | Withdrawn2025-09-26 |
| 2024-04-18 | (unnamed) | Solar | 500 MW | Withdrawn2025-09-26 |
| 2025-04-01 | (unnamed) | Solar | 500 MW | Withdrawn2026-01-05 |
What the record shows
- 2,894 MW of the 3,954 MW filed here withdrew.
- The largest request filed here, 500 MW (solar), withdrew 0.8 years after filing.
- Four requests were filed on 2022-09-15; 2 withdrew and 2 remain active.
- One of the 7 withdrawals came within a year of filing.
- By technology, the requests here were solar 8, battery 1, solar + battery 1.
- The longest-standing active request here was filed on 2022-09-14.
- The dataset records this point of interconnection under two spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Three requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- MISO · IndianaReynolds 345 kV Substation9 requests · 4 built · 2 withdrawn · 3 still in queueRead the record
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- PJM · PennsylvaniaHatfield 500 kV6 requests · 3 built · 3 withdrawn · 0 still in queueRead the record
How the MISO process works today: MISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.