PJM · New Jersey
1,647 MW filed. 105 MW built.
Linden 230 kV
Seven interconnection requests since 2005: 2 reached commercial operation, 3 withdrew, 2 remain active.
- Built
- 2
- Withdrawn
- 3
- Still in queue
- 2
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2005-07-29 | (unnamed) | Gas | 525 MW | Withdrawn2006-03-07 |
| 2006-07-31 | (unnamed) | Oil | 600 MW | Withdrawn2008-10-22 |
| 2007-10-05 | Linden 1 & 2 | Gas | 44 MW | Built2008-06-01 · 0.7 yrs |
| 2013-04-30 | (unnamed) | Gas | 110 MW | Withdrawn2013-11-20 |
| 2013-11-01 | Linden Generating Station | Gas | 61 MW | Built2018-05-16 · 4.5 yrs |
| 2025-04-08 | (unnamed) | Gas | 149.369 MW | Still in queue |
| 2025-04-08 | (unnamed) | Gas | 158.1 MW | Still in queue |
What the record shows
- Three of the seven requests at this node withdrew, and 1,542 MW of the 1,647 MW filed here never reached operation.
- Completions here took between 0.7 and 4.5 years from request to commercial operation.
- The largest request ever filed here, 600 MW, withdrew 2.2 years after filing.
- Two requests were filed on 2025-04-08, and all of them are still active.
- Two of the seven requests were still active at the end of the dataset, so this node's record is not settled.
What a decision record would have to make explicit
- A pattern across seven requests at one node is an observation about this node, not a rate that transfers elsewhere.
- Five of the seven requests are unnamed in the dataset, so nothing here can be attributed to a developer.
- Two requests are unresolved, so any comparison at this node has to stay open rather than concluded.
- The dataset records no withdrawal reasons, study costs or upgrade assignments, so those remain unknowns on this record.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.