Interconnection queue data
Maryland interconnection queue
556 interconnection requests have been filed at points of interconnection in Maryland since 2000, totalling 57 GW. Of that capacity, 9.5% reached commercial operation and 80.1% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 57 GW
- of capacity requested in Maryland since 2000
- 9.5%
- of it reached commercial operation; 80.1% withdrew
- 10 GW
- filed in the last six years (129 requests), of which 53.4% is still in the queue
Which markets Maryland requests sit in
A state is a location, not a market. Requests at Maryland points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| PJM | 556 | 57 GW | 9.5% | 80.1% |
Process pages: PJM.
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 289 | 6 GW | 9.4% | 66.4% | |
| Gas | 100 | 36 GW | 11.9% | 87.8% | |
| Battery | 76 | 6 GW | 0.1% | 45.5% | |
| Other | 54 | 6 GW | 4.3% | 95.7% | |
| Hybrid | 20 | 2 GW | 0.0% | 31.2% | |
| Wind | 17 | 2 GW | 18.4% | 77.0% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 20003 GW
- 20014 GW
- 2002120 MW
- 20034 GW
- 20042 GW
- 200569 MW
- 20064 GW
- 20073 GW
- 20083 GW
- 20093 GW
- 20101 GW
- 20116 GW
- 20122 GW
- 2013597 MW
- 2014581 MW
- 2015642 MW
- 20161 GW
- 20171 GW
- 2018789 MW
- 2019793 MW
- 20202 GW
- 20212 GW
- 20221 GW
- 20232 GW
- 202420 MW
- 20252 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Rock Springs 500kV6 requests in the dataset
- Dickerson 230kV6 requests in the dataset
- Worcester 25kV5 requests in the dataset
- Calvert Cliffs 500kV5 requests in the dataset
- Kelson Ridge 230kV4 requests in the dataset
- Burches Hill-Brandywine 230kV3 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Published retrospectives in Maryland
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.