Tennessee interconnection queue
325 interconnection requests have been filed at points of interconnection in Tennessee since 2000, totalling 124 GW. Of that capacity, 5.0% reached commercial operation and 83.8% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 124 GW
- of capacity requested in Tennessee since 2000
- 5.0%
- of it reached commercial operation; 83.8% withdrew
- 32 GW
- filed in the last six years (133 requests), of which 35.2% is still in the queue
Which markets Tennessee requests sit in
A state is a location, not a market. Requests at Tennessee points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Southeast | 320 | 124 GW | 5.0% | 83.9% | |
| PJM | 5 | 293 MW | 32.4% | 33.4% |
Process pages: PJM.
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Other | 135 | 72 GW | 6.0% | 93.6% | |
| Solar | 96 | 10 GW | 3.0% | 83.4% | |
| Gas | 36 | 31 GW | 5.2% | 59.8% | |
| Hybrid | 29 | 4 GW | 0.0% | 81.5% | |
| Battery | 23 | 3 GW | 0.0% | 73.2% | |
| Wind | 6 | 4 GW | 0.0% | 100.0% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 200022 GW
- 200120 GW
- 20023 GW
- 20042 MW
- 20051 GW
- 200650 MW
- 20072 GW
- 20098 GW
- 20101 GW
- 2011640 MW
- 201293 MW
- 2013936 MW
- 20143 GW
- 20152 GW
- 20161 GW
- 2017927 MW
- 2018762 MW
- 20194 GW
- 20203 GW
- 20215 GW
- 20221 GW
- 20238 GW
- 202414 GW
- 20252 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Raccoon Mountain 161-kV Substation4 requests in the dataset
- Allen 161-kV Substation3 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.