Interconnection queue data
Pennsylvania interconnection queue
1,868 interconnection requests have been filed at points of interconnection in Pennsylvania since 2000, totalling 199 GW. Of that capacity, 14.9% reached commercial operation and 78.8% withdrew.
GridVision AI ResearchPublished Updated
Headline figures
- 199 GW
- of capacity requested in Pennsylvania since 2000
- 14.9%
- of it reached commercial operation; 78.8% withdrew
- 31 GW
- filed in the last six years (748 requests), of which 32.0% is still in the queue
Which markets Pennsylvania requests sit in
A state is a location, not a market. Requests at Pennsylvania points of interconnection are studied by the market that runs the queue there, and the process differs between them.
| Market | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| PJM | 1,814 | 188 GW | 15.7% | 78.6% | |
| NYISO | 49 | 10 GW | 0.0% | 82.0% | |
| MISO | 5 | 1 GW | 12.9% | 87.1% |
By resource type
| Resource | Requests | Capacity filed | Reached operation | Withdrew | Outcome by capacity |
|---|---|---|---|---|---|
| Solar | 813 | 26 GW | 4.2% | 71.8% | |
| Gas | 367 | 116 GW | 19.5% | 80.2% | |
| Other | 235 | 27 GW | 15.5% | 81.2% | |
| Wind | 193 | 14 GW | 11.3% | 85.6% | |
| Hybrid | 143 | 7 GW | 0.0% | 61.1% | |
| Battery | 117 | 9 GW | 0.7% | 77.0% |
Hybrid covers requests the dataset records as a combination, such as solar plus battery.
By year filed
- 200012 GW
- 200115 GW
- 20023 GW
- 20031 GW
- 20044 GW
- 20054 GW
- 200610 GW
- 200710 GW
- 200815 GW
- 20092 GW
- 20102 GW
- 20117 GW
- 20127 GW
- 20134 GW
- 20149 GW
- 201514 GW
- 20163 GW
- 20174 GW
- 20185 GW
- 201911 GW
- 20208 GW
- 20215 GW
- 20227 GW
- 20233 GW
- 20243 GW
- 20255 GW
Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.
Points of interconnection with the most requests
- Montour 230 kV12 requests in the dataset
- Pierce Brook - Lewis Run 230 kV6 requests in the dataset
- Peach Bottom 500kV6 requests in the dataset
- Hatfield 500kV6 requests in the dataset
- South Bend 500kV6 requests in the dataset
- Keystone 500kV6 requests in the dataset
Names are as the dataset records them, so spelling variants of one station can appear separately.
Published retrospectives in Pennsylvania
Method and limits
Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.
For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.
Have a controlled site and a next gate?
GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.
Request a qualification conversationDo not send site records, confidential information, or transaction documents through the public form.