The station filed four times. Its three smallest requests were built.

South Bend 500 kV

Six requests: South Bend Generating Station appears four times, three of which were built, while its own 410 MW request and a 250 MW battery withdrew.

Built
3
Withdrawn
3
Still in queue
0

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2008-12-31(unnamed)Gas400 MWWithdrawn2009-05-28
2013-09-11South Bend Generating StationGas10 MWBuilt2017-01-31 · 3.4 yrs
2013-09-11South Bend Generating StationGas6 MWBuilt2017-01-31 · 3.4 yrs
2018-03-22South Bend Generating StationGas68.1 MWBuilt2022-04-27 · 4.1 yrs
2018-03-22South Bend Generating StationGas410 MWWithdrawn2021-10-20
2021-09-10Armstrong Battery StorageBattery250 MWWithdrawn2025-06-30

What the record shows

  • South Bend Generating Station filed four requests across 2013 and 2018. The three smaller ones — 10 MW, 6 MW and 68.1 MW — were built; the 410 MW request filed alongside the 68.1 MW one withdrew.
  • The two 2013 requests reached commercial operation on the same day, 2017-01-31.
  • On 2018-03-22 the same station filed 68.1 MW and 410 MW together. One was built in 2022; the other withdrew in 2021.
  • 84.1 MW of the 1,144.1 MW filed at this node reached operation.
  • The most recent request, a 250 MW battery, withdrew in June 2025.

What a decision record would have to make explicit

  • Filing one project as several interconnection requests is common across the PJM nodes in this set — it appears at Hatfield, Essex, Kearny, Calvert Cliffs, North Anna and others. It is how the record is structured, not evidence that the approach causes a project to succeed.
  • At this node the same station filed a small and a large request on one day and the outcomes diverged, which the record shows without explaining.
  • The dataset records no withdrawal reasons, study costs or upgrade assignments.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.