The station filed four times. Its three smallest requests were built.
South Bend 500 kV
Six requests: South Bend Generating Station appears four times, three of which were built, while its own 410 MW request and a 250 MW battery withdrew.
- Built
- 3
- Withdrawn
- 3
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2008-12-31 | (unnamed) | Gas | 400 MW | Withdrawn2009-05-28 |
| 2013-09-11 | South Bend Generating Station | Gas | 10 MW | Built2017-01-31 · 3.4 yrs |
| 2013-09-11 | South Bend Generating Station | Gas | 6 MW | Built2017-01-31 · 3.4 yrs |
| 2018-03-22 | South Bend Generating Station | Gas | 68.1 MW | Built2022-04-27 · 4.1 yrs |
| 2018-03-22 | South Bend Generating Station | Gas | 410 MW | Withdrawn2021-10-20 |
| 2021-09-10 | Armstrong Battery Storage | Battery | 250 MW | Withdrawn2025-06-30 |
What the record shows
- South Bend Generating Station filed four requests across 2013 and 2018. The three smaller ones — 10 MW, 6 MW and 68.1 MW — were built; the 410 MW request filed alongside the 68.1 MW one withdrew.
- The two 2013 requests reached commercial operation on the same day, 2017-01-31.
- On 2018-03-22 the same station filed 68.1 MW and 410 MW together. One was built in 2022; the other withdrew in 2021.
- 84.1 MW of the 1,144.1 MW filed at this node reached operation.
- The most recent request, a 250 MW battery, withdrew in June 2025.
What a decision record would have to make explicit
- Filing one project as several interconnection requests is common across the PJM nodes in this set — it appears at Hatfield, Essex, Kearny, Calvert Cliffs, North Anna and others. It is how the record is structured, not evidence that the approach causes a project to succeed.
- At this node the same station filed a small and a large request on one day and the outcomes diverged, which the record shows without explaining.
- The dataset records no withdrawal reasons, study costs or upgrade assignments.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.