Skip to content

Interconnection guide

PTDF, LODF and DC power flow screening, explained

Distribution factors decide which interconnection requests share responsibility for an overloaded line, and they power most early screening. This guide explains what they measure, how grid operators apply them, and where a DC screen stops being reliable.

GridVision AI ResearchPublished Updated

What a PTDF measures

A power transfer distribution factor (PTDF) is the share of a power transfer between two points that flows on a particular transmission facility, expressed as a percentage of the transfer (Overbye, quoting the NERC definition). A PTDF of 20% on a line means that injecting 100 MW at your point of interconnection and withdrawing it elsewhere adds about 20 MW to that line.

In the linear (DC) model, a PTDF does not depend on the size of the transfer, and its magnitude is at most 1 (Kekatos). That is what makes it cheap to compute across thousands of facilities.

What an LODF adds

A line outage distribution factor (LODF) is the portion of a line's pre-outage flow that moves onto another line when the first line is taken out of service (Overbye). With it, the post-outage flow on line ℓ after losing line k is the pre-outage flow on ℓ plus LODF(ℓ,k) times the pre-outage flow on k (Kekatos).

Combining the two gives the outage transfer distribution factor (OTDF): the PTDF of a transfer on line ℓ with line k out of service. Contingency screening in interconnection studies relies on these combinations.

How grid operators use distribution-factor thresholds

In cluster studies, a distribution factor threshold decides whether a request is counted as contributing to an overload, and therefore whether it can be assigned a share of the upgrade.

Distribution factor thresholds used in interconnection studies
OperatorThresholdSource
PJMLoad flow violations are identified where a request has at least a 5% distribution factor (DFAX) on an overload or contributes at least 5% of the facility rating.Manual 14H, Rev. 07
SPP (energy resource service)A 20% or higher distribution factor on facilities overloaded under contingency, or 3% or higher under system-intact conditions.SPP GIP guidelines, May 2025
SPP (network resource service)A 3.0% or higher distribution factor on facilities overloaded in a base case or under contingency.SPP GIP guidelines, May 2025
MISOA 5% distribution factor cutoff groups projects on common constraints; all new projects also undergo AC screening with the full contingency list.BPM-015 redline, 2023

SPP also allocates upgrade costs in proportion to each request's distribution factor multiplied by its megawatts (SPP). A small change in a distribution factor can therefore move a request across a threshold, or change its share of a large upgrade.

What a DC screen cannot tell you

DC power flow assumes lossless lines, voltage magnitudes that are known and constant, reactive power that can be ignored, and small angle differences. Resistive losses are its largest source of error, and accuracy falls as the ratio of resistance to reactance rises (Simpson-Porco). Distribution factors also do not work well for reactive power (Overbye).

  • A DC screen can show real-power (MW) sensitivities and likely thermal overloads.
  • It cannot show voltage, reactive power, stability or short-circuit problems, which operators study separately.
  • Its answer is only as current as the network model, the dispatch assumptions and the queue it was run against.

Use a DC screen to rank candidate sites and to ask better questions, then record its model version, date and limits next to the result. Formal studies remain authoritative. For the site comparison itself, see how to choose a point of interconnection.

Screening a point of interconnection?

GridVision runs deterministic DC screening when authorized network evidence is available, and records the model, version and limits alongside the result in a decision record.

Bring One Live Decision

Sources

Sources checked September 17, 2026. Tariffs, manuals and queue rules change; the governing documents control any live project.