Twelve interconnection requests since 2020: 8 withdrew and 4 remain active.
- Built
- 0
- Withdrawn
- 8
- Still in queue
- 4
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2020-04-15 | SWAN ESS | Battery | 300 MW | Withdrawn2021-04-26 |
| 2020-04-15 | ROADHOUSE STORAGE | Battery | 312.96 MW | Still in queue |
| 2021-04-15 | LAS PILAS | Battery | 204.5175 MW | Withdrawn2023-01-13 |
| 2021-04-15 | JACIVA ENERGY STORAGE | Battery | 403.5 MW | Withdrawn2023-01-13 |
| 2021-04-15 | MAGNOLIA | Battery | 405.656518 MW | Withdrawn2022-12-07 |
| 2021-04-15 | MT BALDY ENERGY STORAGE | Battery | 512.58 MW | Withdrawn2024-07-01 |
| 2023-04-17 | Little Hill | Battery | 63.14 MW | Still in queue |
| 2023-04-17 | Mt Baldy Energy Storage 2 | Battery | 204.93 MW | Still in queue |
| 2023-04-17 | Lizard Spin Energy Center | Battery | 209 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Mule Car | Battery | 227 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Twinkle | Battery | 303.95 MW | Still in queue |
| 2023-04-17 | Marcus Storage | Battery | 304 MW | Withdrawn2024-12-02 |
What the record shows
- 2,566 MW of the 3,451 MW filed here withdrew.
- The largest request filed here, 513 MW (battery), withdrew 3.2 years after filing.
- Six requests were filed on 2023-04-17; 3 withdrew and 3 remain active.
- None of the 8 withdrawals came within a year of filing; the quickest took 1.0 years.
- The longest-standing active request here was filed on 2020-04-15.
- The dataset records this point of interconnection under four spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Four requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.