CAISO · California

Two projects built, four withdrew, from the same two filing windows.

Windhub Substation 230 kV

Sixteen requests since 2007: three reached commercial operation, eight withdrew, five remain active.

Built
3
Withdrawn
8
Still in queue
5

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2007-03-23RISING TREE WIND FARM (FKA HOMESTEAD WIND FARM)Wind198 MWBuilt2015-06-25 · 8.3 yrs
2009-07-31WEST MOJAVE ENERGYSolar350 MWWithdrawn2009-11-02
2009-07-31ORO VERDE SOLAR PROJECT (FKA GATEWAY SOLAR ENERGY PROJECT)Solar150 MWWithdrawn2015-01-13
2011-03-31LOOP RANCH WINDWind299 MWWithdrawn2012-01-04
2016-05-02EDSAN 1Solar + battery118 MWBuilt2023-11-23 · 7.6 yrs
2016-05-02CANELLA SOLAR FARMSolar + battery309.6 MWWithdrawn2018-04-16
2017-05-01CREOSOTESolar418.95 MWWithdrawn2018-02-22
2017-05-01CANELLA 2 SOLAR FARMSolar + battery200 MWWithdrawn2018-04-16
2017-05-01EDSAN 2Solar + battery357 MWBuilt2023-11-10 · 6.5 yrs
2018-04-16BELLEFIELD SOLAR FARMSolar + battery500 MWStill in queue
2018-04-16SANBORN SOLAR 2Solar + battery334 MWStill in queue
2020-04-15ALTA 20 WINDWind257.6 MWWithdrawn2021-03-10
2020-04-15SANBORN 5 HYBRIDSolar560.33 MWStill in queue
2020-04-15BELLEFIELD 3 SOLAR FARMSolar + battery150 MWStill in queue
2020-04-15LONGHORN 1Solar + battery405.8 MWWithdrawn2021-03-11
2020-04-15SANBORN HYBRID 4Solar + battery50 MWStill in queue

What the record shows

  • EDSAN 1 and EDSAN 2 were filed a year apart and reached commercial operation thirteen days apart, in November 2023.
  • CANELLA SOLAR FARM and CANELLA 2 SOLAR FARM were withdrawn on the same date, 2018-04-16, having been filed a year apart.
  • CREOSOTE, the largest request in the 2017 window at 418.95 MW, withdrew within ten months of filing.
  • Both projects that reached commercial operation from the 2016 and 2017 windows were solar-plus-battery; the largest solar-only request in those windows withdrew.
  • The two projects that were built took 7.6 and 6.5 years from request to commercial operation.

What a decision record would have to make explicit

  • Two requests withdrawn on the same day indicates a decision taken across more than one project. The queue record shows the coincidence but not the reasoning.
  • A portfolio decision at this node in 2017 would have been choosing among four requests filed in the same window, of which one was later built.
  • The dataset does not record withdrawal reasons, siting constraints, or study results, so those remain unknowns on this record.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.