CAISO · California
Twenty-two years at one switchyard: gas built, then storage queued.
Otay Mesa Switchyard 230 kV
Fourteen requests since 1999. Every gas project that reached operation was filed before 2018; every request since 2020 is storage, and none has been built.
- Built
- 6
- Withdrawn
- 5
- Still in queue
- 3
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 1999-11-01 | OTAY MESA GENERATING PROJECT | Gas | 550 MW | Built2009-10-02 · 9.9 yrs |
| 2003-01-07 | OTAY MESA | Gas | 65 MW | Built2009-10-02 · 6.7 yrs |
| 2010-02-01 | PIO PICO ENERGY CENTER | Gas | 308 MW | Built2016-11-03 · 6.8 yrs |
| 2014-04-30 | OTAY MESA ENERGY CENTER AGP | Gas | 35 MW | Withdrawn2015-03-24 |
| 2014-04-30 | PIO PICO CAPACITY INCREASE (FKA PIO PICO ENERGY CENTER 2) | Gas | 10 MW | Built2016-12-14 · 2.6 yrs |
| 2015-04-30 | GATEWAY ENERGY STORAGE | Battery | 250 MW | Built2025-04-22 · 10.0 yrs |
| 2015-04-30 | MARIA PICO ENERGY STORAGE CENTER | Battery | 25 MW | Withdrawn2015-07-08 |
| 2015-04-30 | PIO PICO UNIT 4 | Gas | 110 MW | Withdrawn2015-07-08 |
| 2017-02-06 | PIO PICO PLUS | Gas | 18 MW | Built2017-10-17 · 0.7 yrs |
| 2020-04-15 | EAST FIELD ENERGY STORAGE | Battery | 312.96 MW | Still in queue |
| 2021-04-15 | CHARGER STORAGE | Battery | 615.756 MW | Withdrawn2022-12-29 |
| 2021-04-15 | CARGO STORAGE | Battery | 312.96 MW | Still in queue |
| 2021-04-15 | GATEWAY ENERGY STORAGE 2 | Battery | 256.29 MW | Still in queue |
| 2021-04-15 | LA FUENTE ENERGY STORAGE | Battery | 105.9831 MW | Withdrawn2022-12-18 |
What the record shows
- PIO PICO PLUS went from request to commercial operation in 0.7 years; GATEWAY ENERGY STORAGE took 10.0 years from a request filed the same week as two that withdrew within ten weeks.
- The two earliest requests, filed more than three years apart in 1999 and 2003, reached commercial operation on the same day in 2009.
- Every request filed from 2020 onwards is battery storage. Two withdrew in December 2022 and three were still active at the end of the dataset.
- Four requests were filed on 2021-04-15 totalling 1,291 MW of storage; two of them withdrew eight days apart in December 2022.
- Of the six projects that reached operation, five are gas and the sixth is the 250 MW battery that took a decade.
What a decision record would have to make explicit
- The spread between the fastest and slowest completion at this node is 0.7 to 10.0 years, so an assumption drawn from one project here would not transfer to the next.
- Requests filed on the same day resolved as far apart as ten years, so filing date ordered nothing at this node.
- The dataset records no withdrawal reasons and no study results, so the shift from gas to storage is a description of what was filed, not of what the network allowed.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.