CAISO · California

Fourteen years, three technologies, and one project that waited 12.9 years.

Whirlwind Substation 230 kV

Twenty-three requests since 2006 at one substation: wind gave way to solar, then to solar-plus-battery, and six projects reached operation.

Built
6
Withdrawn
10
Still in queue
7

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2006-11-22ALTA Q153 (FKA ALTA 7)Wind100 MWWithdrawn2014-09-29
2007-02-21ALTA Q175 (FKA ALTA 11)Wind650 MWWithdrawn2015-06-12
2008-03-31GASKELL SOLAR GENERATING STATIONSolar264 MWWithdrawn2008-11-26
2008-05-30AV SOLAR ONE PROJECTSolar250 MWBuilt2014-06-19 · 6.1 yrs
2009-07-31DESERT VIEW SUNTOWERSolar141 MWWithdrawn2015-11-05
2009-07-31ROSAMOND WEST SOLARSolar + battery299.6 MWStill in queue
2010-02-01CATALINA SOLARSolar145.44 MWBuilt2022-12-29 · 12.9 yrs
2010-02-01MOJAVALON ISolar146 MWWithdrawn2010-04-20
2011-03-31WILLOW SOLARSolar100 MWWithdrawn2012-04-03
2015-04-30GOLDEN PRISMBattery6 MWWithdrawn2019-03-18
2015-04-30WILLOW SPRINGS SOLAR 4Battery75 MWStill in queue
2015-04-30ROSAMOND SOUTH EASTSolar + battery100 MWBuilt2025-08-12 · 10.3 yrs
2015-04-30ANTELOPE VALLEY COMPLEXSolar + battery100 MWBuilt2025-05-08 · 10.0 yrs
2016-05-02WILLY 9Solar + battery174 MWBuilt2025-05-08 · 9.0 yrs
2016-05-02SOLAR STAR 3Solar + battery25 MWStill in queue
2016-05-02SOLAR STAR 4Solar + battery25.05 MWStill in queue
2016-05-02CYCLONE SOLARSolar + battery40 MWBuilt2025-08-01 · 9.2 yrs
2016-05-02LINWOOD SOLAR FARMSolar + battery205.2 MWWithdrawn2017-04-19
2017-05-01CAMINO SOLARSolar + battery44.88 MWStill in queue
2018-04-16LONGSPUR 11Solar + battery182.46 MWWithdrawn2019-03-12
2020-04-15KEYHOLE WINDWind100 MWStill in queue
2020-04-15KEYHOLE WIND 2Wind100 MWWithdrawn2020-06-25
2020-04-15WILLOW ROCK ENERGY STORAGEStorage512 MWStill in queue

What the record shows

  • CATALINA SOLAR was filed on 2010-02-01 and reached commercial operation on 2022-12-29 — 12.9 years, the longest resolved wait in this set.
  • The technology at this node turned over twice: the two wind requests of 2006 and 2007 both withdrew, solar dominated the 2008 to 2011 filings, and every request from 2015 onwards except two carries storage.
  • Four of the six projects that reached operation did so in 2025, from requests filed in 2015 and 2016.
  • MOJAVALON I withdrew eleven weeks after filing; ALTA Q153 stayed in the queue for nearly eight years before withdrawing.
  • Seven of the twenty-three requests were still active at the end of the dataset, including a 512 MW standalone storage project filed in 2020.

What a decision record would have to make explicit

  • The dataset records six further requests at this substation under a second spelling of its name, with and without a space before kV. A query keyed on the name alone would miss roughly a quarter of the node.
  • Requests filed on one day at this node resolved years apart, so filing date did not order the outcomes.
  • The dataset records no withdrawal reasons, so the technology turnover is a description of what was filed, not an explanation of what succeeded.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.