CAISO · California · Public-record retrospective
Arco Substation 70 kV: interconnection queue history
Eleven of twelve requests withdrew; one is still in the queue.
GridVision AI ResearchUpdated
Twelve interconnection requests since 2009: 11 withdrew and 1 remains active.
- Built
- 0
- Withdrawn
- 11
- Still in queue
- 1
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2009-08-21 | KINGSOLAR (FKA QUAY VALLEY 20MW SOLAR PV) | Solar | 20 MW | Withdrawn2012-07-31 |
| 2010-09-29 | LAS LOMAS SOLAR | Solar | 20 MW | Withdrawn2012-08-10 |
| 2010-09-29 | SOUTH DOME SOLAR | Solar | 20 MW | Withdrawn2012-08-10 |
| 2010-09-30 | ORION KERN COUNTY SOLAR I | Solar | 20 MW | Withdrawn2011-03-08 |
| 2011-03-31 | KINGSOLAR I | Solar | 20 MW | Withdrawn2012-04-17 |
| 2011-03-31 | KINGSOLAR III | Solar | 20 MW | Withdrawn2012-04-17 |
| 2014-04-30 | BROKEN SPOKE | Solar | 20 MW | Withdrawn2016-04-22 |
| 2014-04-30 | MAGELLAN SOLAR | Solar | 20 MW | Withdrawn2015-03-24 |
| 2014-04-30 | PANDORA SOLAR | Solar | 60 MW | Withdrawn2016-06-03 |
| 2015-04-30 | ALAMO SPRINGS SOLAR 2 | Solar + battery | 50 MW | Withdrawn2021-05-17 |
| 2015-04-30 | ALAMO SPRINGS SOLAR 1 | Solar + battery | 80 MW | Withdrawn2021-05-17 |
| 2018-04-16 | AZALEA | Solar + battery | 61.3 MW | Still in queue |
What the record shows
- 350 MW of the 411 MW filed here withdrew.
- The largest request filed here, 80 MW (solar + battery), withdrew 6.0 years after filing.
- Three requests were filed on 2014-04-30; all of them withdrew.
- Two of the 11 withdrawals came within a year of filing.
- By technology, the requests here were solar 9, solar + battery 3.
- The longest-standing active request here was filed on 2018-04-16.
- The dataset records this point of interconnection under seven spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- One request is unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.