CAISO · California · Public-record retrospective
Lugo 500 kV: interconnection queue history
Seven of eighteen requests withdrew; eleven are still in the queue.
GridVision AI ResearchUpdated
Eighteen interconnection requests since 2021: 7 withdrew and 11 remain active.
- Built
- 0
- Withdrawn
- 7
- Still in queue
- 11
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2021-04-15 | CONDUIT ENERGY STORAGE | Battery | 512.58 MW | Still in queue |
| 2023-04-17 | Castle Rock Energy Storage | Battery | 157.6 MW | Withdrawn2025-12-12 |
| 2023-04-17 | Comstock | Gas + battery | 199 MW | Still in queue |
| 2023-04-17 | Conduit Energy Storage 2 | Battery | 199 MW | Still in queue |
| 2023-04-17 | Cabrera Reliability | Battery | 205.403 MW | Still in queue |
| 2023-04-17 | Duran | Gas + battery | 300 MW | Still in queue |
| 2023-04-17 | RIGHTEOUS ENERGY STORAGE | Battery | 500 MW | Withdrawn2025-12-01 |
| 2023-04-17 | Summiy Valley | Battery | 504.73 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Ambar Energy Storage | Battery | 504.9 MW | Still in queue |
| 2023-04-17 | Galicia Storage | Battery | 505.6459 MW | Still in queue |
| 2023-04-17 | Goldspur | Battery | 506.95128 MW | Withdrawn2025-05-30 |
| 2023-04-17 | Victorious | Battery | 516 MW | Withdrawn2025-12-03 |
| 2023-04-17 | Chronos Energy Storage | Storage | 516.8 MW | Still in queue |
| 2023-04-17 | Lupine Energy Center | Battery | 518.0683 MW | Still in queue |
| 2023-04-17 | Summit Valley Energy Storage | Battery | 518.6815 MW | Still in queue |
| 2023-04-17 | Aviation | Gas + battery | 600 MW | Still in queue |
| 2023-04-17 | Date Palm | Battery | 620.58 MW | Withdrawn2025-12-01 |
| 2023-04-17 | Hideout | Gas + battery | 1100 MW | Withdrawn2024-12-02 |
What the record shows
- 3,906 MW of the 8,486 MW filed here withdrew.
- The largest request filed here, 1,100 MW (gas + battery), withdrew 1.6 years after filing.
- Seventeen requests were filed on 2023-04-17; 7 withdrew and 10 remain active.
- None of the 7 withdrawals came within a year of filing; the quickest took 1.6 years.
- By technology, the requests here were battery 13, gas + battery 4, storage 1.
- The longest-standing active request here was filed on 2021-04-15.
- The dataset records this point of interconnection under three spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Eleven requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.