Six withdrawals, and one 405.85 MW project.
Devers Substation 230 kV
Eight interconnection requests since 2014: 1 reached commercial operation, 6 withdrew, 1 remain active.
- Built
- 1
- Withdrawn
- 6
- Still in queue
- 1
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2014-04-30 | VERMILLION | Solar | 100 MW | Withdrawn2015-01-27 |
| 2016-05-02 | MARVEL | Battery | 405.85 MW | Built2024-04-24 · 8.0 yrs |
| 2018-04-16 | SILVERWING | Solar + battery | 156 MW | Withdrawn2019-03-12 |
| 2019-04-15 | CONSECHA | Battery | 100.98 MW | Withdrawn2019-07-10 |
| 2019-04-15 | VENTUS RENEWABLE ENERGY CENTER | Solar + wind + battery | 208.527 MW | Withdrawn2019-07-19 |
| 2020-04-15 | DESERT SANDS | Battery | 300 MW | Still in queue |
| 2020-04-15 | GRISEDALE STORAGE 1 | Battery | 510 MW | Withdrawn2021-05-10 |
| 2021-04-15 | ARDILLA | Battery | 410.76 MW | Withdrawn2025-10-02 |
What the record shows
- Six of the eight requests at this node withdrew, and 1,786 MW of the 2,192 MW filed here never reached operation.
- The one project that reached operation, 405.85 MW of battery, took 8 years from request to commercial operation.
- The largest request ever filed here, 510 MW, withdrew 1.1 years after filing.
- Two requests were filed on 2019-04-15, and all of them withdrew.
- Four technologies were filed here: Solar, Battery, Solar + battery and solar + wind + battery.
What a decision record would have to make explicit
- A pattern across eight requests at one node is an observation about this node, not a rate that transfers elsewhere.
- One request is unresolved, so any comparison at this node has to stay open rather than concluded.
- The dataset records no withdrawal reasons, study costs or upgrade assignments, so those remain unknowns on this record.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.