Los Banos 500 kV: interconnection queue history

Eleven of thirteen requests withdrew; two are still in the queue.

GridVision AI ResearchUpdated

Thirteen interconnection requests since 2021: 11 withdrew and 2 remain active.

Built
0
Withdrawn
11
Still in queue
2

The queue record

Every interconnection request the dataset records at this point of interconnection, in filing order.

Interconnection requests recorded at this point of interconnection, with request date, capacity and outcome.
RequestedProjectTechnologyCapacityOutcome
2021-04-15WINGTIP SOLAR 2Solar + battery561.5 MWWithdrawn2023-01-30
2021-04-15WINGTIP SOLAR 1Solar + battery1176.1 MWStill in queue
2023-04-17Copper CloudBattery200 MWWithdrawn2025-12-03
2023-04-17FoothillsSolar + battery206 MWWithdrawn2024-12-02
2023-04-17Mystic RidgeSolar + battery206.1 MWWithdrawn2025-12-04
2023-04-17Foothills (Formly Spring Bath Hybrid)Solar + battery208 MWWithdrawn2024-12-02
2023-04-17CRESTLEYBattery270 MWWithdrawn2025-12-03
2023-04-17Lotus 3Battery400 MWWithdrawn2024-12-02
2023-04-17SilkieBattery400 MWWithdrawn2025-12-03
2023-04-17Carissalito CreekSolar + battery415.86 MWStill in queue
2023-04-17Leopard StorageBattery458.703 MWWithdrawn2025-05-29
2023-04-17BacaBattery490.734 MWWithdrawn2025-12-01
2023-04-17Greyhound StorageBattery1000 MWWithdrawn2024-12-02

What the record shows

  • 4,401 MW of the 5,993 MW filed here withdrew.
  • The largest request filed here, 1,176 MW (solar + battery), was filed in 2021 and is still active.
  • Eleven requests were filed on 2023-04-17; 10 withdrew and 1 remains active.
  • None of the 11 withdrawals came within a year of filing; the quickest took 1.6 years.
  • By technology, the requests here were battery 7, solar + battery 6.
  • The longest-standing active request here was filed on 2021-04-15.
  • The dataset records this point of interconnection under four spellings, which are combined here.

What a decision record would have to make explicit

  • None of the resolved requests at this node reached operation, and the public record does not say why.
  • Two requests are unresolved, so the outcome counts at this node can still change.
  • The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.

What this does and does not show

This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.