CAISO · California · Public-record retrospective
Red Bluff Substation 500 kV: interconnection queue history
Six of ten requests withdrew; four are still in the queue.
GridVision AI ResearchUpdated
Ten interconnection requests since 2015: 6 withdrew and 4 remain active.
- Built
- 0
- Withdrawn
- 6
- Still in queue
- 4
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2015-04-30 | EAGLE MOUNTAIN PUMP STORAGE #4 | Storage | 1408 MW | Withdrawn2016-02-12 |
| 2018-04-16 | IRON HILLS PUMPED STORAGE | Storage | 1407 MW | Withdrawn2019-03-08 |
| 2019-04-15 | LYCAN SOLAR | Solar + battery | 400 MW | Still in queue |
| 2019-04-15 | OBERON | Solar + battery | 518.4 MW | Still in queue |
| 2020-04-15 | ETERNAL PUMPED STORAGE | Battery + storage | 1400 MW | Withdrawn2023-12-21 |
| 2021-04-15 | EASLEY | Solar + battery | 290 MW | Still in queue |
| 2021-04-15 | ETERNAL 2 | Battery + storage | 1434.4 MW | Withdrawn2025-08-14 |
| 2023-04-17 | Lycan Solar 2 | Solar | 192.2176 MW | Still in queue |
| 2023-04-17 | Laramide Storage | Battery | 1000 MW | Withdrawn2024-12-02 |
| 2023-04-17 | Skylar Verano Solar | Solar + battery | 1026 MW | Withdrawn2024-12-02 |
What the record shows
- 7,675 MW of the 9,076 MW filed here withdrew.
- The largest request filed here, 1,434 MW (battery + storage), withdrew 4.3 years after filing.
- Three requests were filed on 2023-04-17; 2 withdrew and 1 remains active.
- Two of the 6 withdrawals came within a year of filing.
- By technology, the requests here were solar + battery 4, battery + storage 2, storage 2, battery 1, solar 1.
- The longest-standing active request here was filed on 2019-04-15.
- The dataset records this point of interconnection under four spellings, which are combined here.
What a decision record would have to make explicit
- None of the resolved requests at this node reached operation, and the public record does not say why.
- Four requests are unresolved, so the outcome counts at this node can still change.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.