CAISO · California · Public-record retrospective
Schindler Substation 115 kV Bus: interconnection queue history
Nine requests and 613 MW filed. None built.
GridVision AI ResearchUpdated
Nine interconnection requests since 2010: 9 withdrew.
- Built
- 0
- Withdrawn
- 9
- Still in queue
- 0
The queue record
Every interconnection request the dataset records at this point of interconnection, in filing order.
| Requested | Project | Technology | Capacity | Outcome |
|---|---|---|---|---|
| 2010-01-06 | EXCELSIOR SOLAR | Solar | 20 MW | Withdrawn2013-10-30 |
| 2010-07-20 | GRAHAM SOLAR FARM I | Solar | 20 MW | Withdrawn2012-03-06 |
| 2010-07-31 | LAGUNA SOLAR FARM | Solar | 200 MW | Withdrawn2013-05-03 |
| 2011-03-31 | GRAHAM SOLAR FARM I EXPANSION | Solar | 20 MW | Withdrawn2012-04-17 |
| 2011-03-31 | GRAHAM SOLAR FARM II | Solar | 20 MW | Withdrawn2012-04-17 |
| 2011-03-31 | GRAHAM SOLAR FARM II EXPANSION | Solar | 20 MW | Withdrawn2012-04-17 |
| 2018-04-16 | STEPHEN | Solar | 102.73 MW | Withdrawn2019-03-13 |
| 2018-04-16 | DERNOPI SOLAR | Solar | 103.3 MW | Withdrawn2019-02-22 |
| 2023-04-17 | Soleado | Solar + battery | 107 MW | Withdrawn2024-12-02 |
What the record shows
- 613 MW of the 613 MW filed here withdrew.
- The largest request filed here, 200 MW (solar), withdrew 2.8 years after filing.
- Three requests were filed on 2011-03-31; all of them withdrew.
- Two of the 9 withdrawals came within a year of filing.
- By technology, the requests here were solar 8, solar + battery 1.
- The dataset records this point of interconnection under five spellings, which are combined here.
What a decision record would have to make explicit
- Every request at this node withdrew. The public record does not say why, so a new request here would have to rest on its own study evidence rather than on this history.
- The dataset records outcomes and dates, not reasons, so no cause is attributed to any outcome here.
What this does and does not show
This is a reading of a public dataset, not a customer case study: no engagement, customer or client is involved. The dataset records outcomes — what was built, what withdrew, and when — but not why any project withdrew, so no cause is attributed here. Nothing on this page claims GridVision predicted, influenced or would have changed any outcome, and a pattern at one point of interconnection does not generalise to another.
Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition — project-level interconnection queue dataset. Interconnection requests through year-end 2025. Used under CC BY 4.0; attribution to Lawrence Berkeley National Laboratory and GridTracker.
Related points of interconnection
- CAISO · CaliforniaColorado River Substation 230 kV16 requests · 3 built · 11 withdrawn · 2 still in queueRead the record
- CAISO · CaliforniaWindhub Substation 230 kV16 requests · 3 built · 8 withdrawn · 5 still in queueRead the record
- CAISO · CaliforniaWhirlwind Substation 230 kV23 requests · 6 built · 10 withdrawn · 7 still in queueRead the record
- CAISO · CaliforniaOtay Mesa Switchyard 230 kV14 requests · 6 built · 5 withdrawn · 3 still in queueRead the record
How the CAISO process works today: CAISO interconnection queue. Comparing candidate nodes for a project? Read how to choose a point of interconnection.