Earlier work (2025–2026). GridVision now focuses on data-center site advancement and cross-gate coordination for controlled sites in Northern Virginia. The interconnection-queue research below is kept for reference and retains the vocabulary of the period in which it was written; it is not a current product.

Interconnection queue data

Nevada interconnection queue

644 interconnection requests have been filed at points of interconnection in Nevada since 2004, totalling 161 GW. Of that capacity, 2.9% reached commercial operation and 51.5% withdrew.

GridVision AI ResearchPublished Updated

Headline figures

161 GW
of capacity requested in Nevada since 2004
2.9%
of it reached commercial operation; 51.5% withdrew
106 GW
filed in the last six years (326 requests), of which 59.5% is still in the queue

Which markets Nevada requests sit in

A state is a location, not a market. Requests at Nevada points of interconnection are studied by the market that runs the queue there, and the process differs between them.

MarketRequestsCapacity filedReached operationWithdrewOutcome by capacity
West523126 GW3.0%46.8%
CAISO12134 GW2.4%69.1%

Process pages: CAISO.

By resource type

ResourceRequestsCapacity filedReached operationWithdrewOutcome by capacity
Hybrid26893 GW1.1%49.2%
Solar16723 GW14.9%72.2%
Battery8922 GW0.0%33.5%
Other8610 GW2.8%48.8%
Gas219 GW0.0%51.0%
Wind134 GW0.0%88.9%

Hybrid covers requests the dataset records as a combination, such as solar plus battery.

By year filed

  • 200410 MW
  • 20051 GW
  • 20064 GW
  • 20072 GW
  • 20081 GW
  • 20092 GW
  • 20103 GW
  • 20112 GW
  • 20124 GW
  • 20132 GW
  • 20142 GW
  • 20152 GW
  • 20164 GW
  • 20174 GW
  • 201812 GW
  • 201910 GW
  • 20207 GW
  • 202118 GW
  • 202219 GW
  • 202342 GW
  • 20245 GW
  • 202515 GW

Recent years are unsettled: requests filed in the last few years may still be built or withdrawn.

Points of interconnection with the most requests

  • VALLEY SWITCH 230 kV8 requests in the dataset
  • Trout Canyon Substation 230 kV7 requests in the dataset
  • Mohave Substation 500kV5 requests in the dataset
  • Control Substation 115kV bus5 requests in the dataset
  • Gamebird Substation 230 kV3 requests in the dataset
  • Vista Substation 138kV3 requests in the dataset

Names are as the dataset records them, so spelling variants of one station can appear separately.

Published retrospectives in Nevada

Method and limits

Each request is counted once, at the capacity and status the dataset records for it, and placed in the state the dataset gives for its point of interconnection. Requests missing a state, status, filing year or capacity are left out. The dataset records outcomes and dates, not reasons, so nothing here says why a request withdrew, and no share is a rate to plan against.

For the same record filtered your own way, use the queue explorer; for national tables and time-to-build figures, see queue statistics.

Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, data file through 2025, CC BY 4.0. Computed September 18, 2026.

Have a controlled site and a next gate?

GridVision qualifies a limited number of Northern Virginia data-center sites for a Site Evidence Record and 90-Day Gate Closure Plan. The public form collects contact details only.

Request a qualification conversation

Do not send site records, confidential information, or transaction documents through the public form.